APM Project Fundamentals Qualification (PFQ) Questions and Answers

Question 121

What is the most likely result of providing effective quality management in the project?

Options:

A.

The project outputs will have been delivered.

B.

Conformance of the outputs and processes to requirements will result in a product that is fit for purpose.

C.

The project management plan will have been followed

D.

Customer expectations will have been exceeded with both outputs and processes

Question 122

A procurement strategy is a:

Options:

A.

technical specification.

B.

day-to-day requirement.

C.

detailed timetable.

D.

high-level approach.