Question 37

Which of the following are challenges for a project manager developing and leading a project team?

1) Issues and incompatibility amongst team members

2) Getting the right skills and attributes amongst team members

3) Co-location of team members in the same geographic area

4) Lack of accountability of team members

Options:

A.

1, 2 & 3

B.

1, 2 & 4

C.

1, 3 & 4

D.

2, 3 & 4

Question 38

Scope management in an iterative life cycle would ensure that:

Options:

A.

the must have' requirements are given the top priority for delivery.

B.

the scope is identified at a deeper level in the project.

C.

all stakeholders get what they want from the project.

D.

areas of the project that will be delivered are fully agreed

Question 39

What would be the effect if the resources required for a project's critical path activities were insufficient?

Options:

A.

It would reduce the project duration.

B.

It would extend the project duration.

C.

The quality of the deliverables would suffer.

D.

Resource smoothing should be applied to the critical path.

Question 40

Which one of the following is the best description of project scope?

Options:

A.

Scope is detailed in the business case.

B.

Scope is the total work content of a project.

C.

Scope is an outcome of the scheduling and estimating processes.

D.

Scope defines what is NOT delivered by the project.