Project Fundamentals Qualification APM-PFQ Syllabus Exam Questions Answers

Page: 20 / 31
Total 409 questions

APM Project Fundamentals Qualification (PFQ) Questions and Answers

Question 77

Which one of the following statements is true?

Options:

A.

Business-as-usual activities cannot be improved.

B.

Business-as-usual activities are more difficult to manage than projects.

C.

Projects are transient endeavours that bring about change to business-as-usual.

D.

A. project is always the starting point for operational refinement.

Question 78

A Responsibility Assignment Matrix (RAM) can be used to:

Options:

A.

define the terms of reference of the project manager.

B.

define the limits of the project sponsor's responsibilities.

C.

allocate risk management response activities to project personnel.

D.

allocate work packages to those responsible for project work.

Question 79

Which of the following is an activity in a typical configuration management process?

Options:

A.

Evaluation.

B.

Identification.

C.

Registration.

D.

Justification.

Question 80

The primary purpose of a product breakdown structure (PBS) is to:

Options:

A.

define all the products that the project will produce.

B.

define precisely what resources will be used on the project.

C.

detail all the products in order of priority.

D.

map out the key project elements identified in the business plan