Question 113

Which stakeholders are likely to form the main part of a project governance board?

Options:

A.

Project sponsor, project manager and quality manager.

B.

Corporate management, project sponsor, quality manager and project office.

C.

Sponsor, supplier representative and user representative.

D Sponsor, project manager and senior project team members.

Question 114

Three general categories for interpretation of communication could be described as:

Options:

A.

email, paper, Voice.

B.

tactile/visual, auditory, written.

C.

telephone, computer. microphone.

D.

reception, transmission, interruption.

Question 115

When is an analysis of a project's environment most likely to be undertaken?

Options:

A.

In the Definition Phase

B.

In the Transition Phase

C.

In the Concept Phase

D.

In the Deployment Phase

Question 116

A project communication plan identifies the relevant information that should be communicated to:

Options:

A.

the project team.

B.

the project stakeholders.

C.

the project board.

D.

the project sponsor