Question 29

The post project review report should be:

Options:

A.

included in the project plan for the next similar project.

B.

restricted in circulation in case it contains critical information.

C.

archived for use in a future audit of project management processes.

D.

available to all project managers within the organisation

Question 30

Which statement best describes a responsibility of the project team members?

Options:

A.

To establish formal reporting procedures for project progress.

B.

To assess the progress of their work against the strategic objectives.

C.

To ensure that work assigned to them by the Project Manager is performed.

D.

To identify and resolve project issues affecting the work delegated to them

Question 31

Which one of the following statements is true?

Options:

A.

Risk events always have beneficial effects on the project.

B.

Risk events can have either beneficial or detrimental effects on the project.

C.

Risk events always have detrimental effects on the project.

D.

Risk events have neither beneficial nor detrimental effects on the project.

Question 32

What role does the project manager have in the writing of the business case? The project manager:

Options:

A.

works with the project sponsor.

B.

has no involvement.

C.

must develop it themself.

D.

works with the end user.