Question 85

Product breakdown structures illustrate the required scope of work by a hierarchical structure itemising the:

Options:

A.

components of each product.

B.

budget of each product.

C.

benefits of each product.

D.

risks of each product.

Question 86

One of the benefits of developing communication plans in projects is that this ensures:

Options:

A.

the power and influence of stakeholders is understood.

B.

that all communication is delivered face to face.

C.

your message is understood.

D.

clear reporting lines for the project.

Question 87

Controlling or influencing project success factors will:

Options:

A.

increase the likelihood of a successful project.

B.

ensure senior management support.

C.

measure progress towards a successful conclusion.

D.

ensure project completion.

Question 88

The role of a leader includes:

Options:

A.

effectively managing risks.

B.

selecting the project team.

C.

coaching and mentoring project staff.

D.

producing accurate project reports.