Big Halloween Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

PMI CAPM CAPM New Questions

Page: 47 / 98
Total 1305 questions

Certified Associate in Project Management (CAPM) Questions and Answers

Question 185

A project is at risk of delivering the solution late because of poor quality that prevents the user acceptance testing (UAT) from being finalized. The product owner does not want to sign off until all the Severity 1 (S1) defects are fixed. What should the project manager do to manage this risk?

Options:

A.

Create a risk in the risk register for each S1 defect and assign actions.

B.

Consult the risk register and implement the risk response actions.

C.

Ask the developers to work longer hours and resolve the defects.

D.

Review the organizational chart to find out who else can sign off UAT.

Question 186

Which of the following answers includes an input, a technique, and an output of the Plan Stakeholders Engagement process?

Options:

A.

Project management plan, data gathering, and stakeholder engagement plan

B.

Business documents, meetings, and stakeholder register

C.

Organizational process assets, data gathering, and project document updates

D.

Project management plan, data analysis, and change requests

Question 187

A project's aim, from a business perspective, is moving an organization from one level to another to achieve a specific objective. What is the goal for a project's successful completion?

Options:

A.

Current state

B.

Future state

C.

Budgeted state

D.

Planned state

Question 188

In one of the project meetings during a project execution, a new stakeholder attends and highlights a new risk. What should the project manager do next?

Options:

A.

Add this risk to the lessons learned register on project completion.

B.

Add the stakeholder to the stakeholder register and add the risk to the risk register.

C.

Make sure proper testing gets completed to minimize the risk highlighted.

D.

Ignore the risk from this stakeholder as this stakeholder never showed up at the start of the project.

Page: 47 / 98
Total 1305 questions