Weekend Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

CAPM Premium Exam Questions

Page: 10 / 100
Total 1250 questions

Certified Associate in Project Management (CAPM) Questions and Answers

Question 37

Which of the following is developed from the project scope baseline and defines only that portion of the project scope that is to be included within a related contract?

Options:

A.

Product scope description

B.

Procurement statement of work

C.

Project schedule

D.

Work breakdown structure (WBS)

Question 38

Monte Carlo is which type of risk analysis technique?

Options:

A.

Probability

B.

Quantitative

C.

Qualitative

D.

Sensitivity

Question 39

Which of the following events would result in a baseline update?

Options:

A.

A project is behind schedule and the project manager wants the baseline to reflect estimated actual completion.

B.

A customer has approved a change request broadening the project scope and increasing the budget.

C.

One of the risks identified in the risk management plan occurs, resulting in a schedule delay.

D.

One of the key project team resources has left the team and no replacement is available.

Question 40

During which process would stakeholders provide formal acceptance of the completed project scope?

Options:

A.

Perform Quality Control

B.

Verify Scope

C.

Control Scope

D.

Develop Schedule

Page: 10 / 100
Total 1250 questions