Summer Certification Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

CAPM Premium Exam Questions

Page: 10 / 99
Total 1326 questions

Certified Associate in Project Management (CAPM) Questions and Answers

Question 37

When is a project finished?

Options:

A.

After verbal acceptance of the customer or sponsor

B.

After lessons learned have been documented in contract closure

C.

When the project objectives have been met

D.

After resources have been released

Question 38

Information collected on the status of project activities being performed to accomplish the project work is known as what?

Options:

A.

Project management information system

B.

Work performance information

C.

Work breakdown structure

D.

Variance analysis

Question 39

A project manager has a project schedule baseline. How can the critical path be determined from the finalized schedule?

Options:

A.

Identify the crashed project schedule to find the shortest duration to complete the project.

B.

Identify the longest activity path in the schedule with the shortest possible duration.

C.

Identify the tasks with float duration, which do not impact the duration of the project.

D.

Identify the path through the schedule with leveled resources and the shortest duration.

Question 40

Which contract type is least desirable to a vendor?

Options:

A.

Fixed price with economic price adjustment (FPEPA)

B.

Firm fixed price (FFP)

C.

Cost plus fixed fee (CPFF >

D.

Cost plus award fee (CPAF >

Page: 10 / 99
Total 1326 questions