Weekend Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

CAPM Reviews Questions

Page: 26 / 99
Total 1317 questions

Certified Associate in Project Management (CAPM) Questions and Answers

Question 101

Which project management process is used by the project manager to ensure that stakeholders receive timely and relevant information?

Options:

A.

Plan Communications Management

B.

Manage Communications

C.

Monitor Communications

D.

Develop Project Management Plan

Question 102

The project manager is leading a construction project that has been ongoing for eight years. The project manager needs to calculate the correct static payback period and consults the cash flow statement of the construction project investment.

What equation should the project manager use?

Options:

A.

Static payback period = 6 + 1300 / 500 = 6.6

B.

Static payback period = 3 + 1200 / 500 = 5.4

C.

Static payback period = 5 + 700 / 500 = 5.4

D.

Static payback period = 5 + 200 / 500 = 5.4

Question 103

A product owner asked for a change in one of the requirements during the elicitation phase. What should the business analyst do?

Options:

A.

Provide the information to the product manager for approval.

B.

Provide the information to the project manager to seek approval or rejection.

C.

Reject the change as the project scope has already been defined.

D.

Accept the modification and update the requirements traceability matrix.

Question 104

A project receives budget approval, but the risk of extra costs is expected. Which of these inputs should the project manager check in order to make a qualitative risk analysis?

Options:

A.

The risk management plan and the assumption log

B.

Costs estimates and cost forecast

C.

The risk management plan and the basis of estimates

D.

The assumption log and the project charter

Page: 26 / 99
Total 1317 questions