Which activity is an input to the Conduct Procurements process?
Organizational process assets
Resource availability
Perform Integrated Change Control
Team performance assessment
When is a project finished?
After verbal acceptance of the customer or sponsor
After lessons learned have been documented in contract closure
When the project objectives have been met
After resources have been released
An output of Control Schedule is:
A project schedule network diagram
A schedule management plan
Schedule data
Schedule forecasts
What is the probability of occurrence if the risk rating is 0.56 and the impact if the risk does occur is very high (0.80)?
0.45
0.56
0.70
1.36