Summer Certification Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

CAPM CAPM Exam Questions and Answers PDF

Page: 38 / 99
Total 1326 questions

Certified Associate in Project Management (CAPM) Questions and Answers

Question 149

A method of obtaining early feedback on requirements by providing a working model of the expected product before actually building is known as:

Options:

A.

Benchmarking.

B.

Context diagrams.

C.

Brainstorming.

D.

Prototyping.

Question 150

During the execution of a project, a stakeholder asks a project manager whether the project is falling behind or ahead of its baseline schedule. The project manager calculates the earned value analysis (EVA) schedule variance and it comes out to be zero. Which of the following is correct about the EVA schedule variance?

Options:

A.

It is calculated incorrectly, as it cannot be zero for an in-flight project; otherwise the project is completed.

B.

Change it to a negative value to show that the project is falling behind.

C.

Zero is a perfectly valid value for an in-flight project; hence share the zero value with the stakeholder.

D.

Change it to a positive value to show that the project is ahead of its baseline schedule.

Question 151

Which type of contract is most commonly used by buying organizations because the price for goods is set at the outset and is not subject to change unless the scope of work changes?

Options:

A.

Fixed Price with Economic Price Adjustments Contract (FP-EPA)

B.

Cost-Reimbursable Contract (CR)

C.

Firm-Fixed -Price Contract (FFP)

D.

Fixed-Price-Incentive-Fee Contract (FPIF)

Question 152

What are the Project Procurement Management processes?

Options:

A.

Conduct Procurements, Control Procurements, Integrate Procurements, and Close Procurements

B.

Estimate Procurements, Integrate Procurements, Control Procurements, and Validate Procurements

C.

Plan Procurement Management, Conduct Procurements, Control Procurements, and Close Procurements

D.

Plan Procurement Management, Perform Procurements, Control Procurements, and Validate Procurements

Page: 38 / 99
Total 1326 questions