Certified Associate in Project Management (CAPM) Questions and Answers

Question 85

Which of the following does a portfolio combine?

Options:

A.

Projects, programs, and operations

B.

Operations, strategies, and business continuity

C.

Projects, programs, and risks

D.

Projects, change management, and operations

Question 86

A project lead asks the team to create a work breakdown structure (WBS) of the project's scope. The team is confused about how far they should break down the scope.

What should the project lead tell the team?

Options:

A.

Decompose to the activity or task level.

B.

Decompose until all of the risks are identified.

C.

Decompose to the work package level.

D.

Decompose until a WBS dictionary is obtained.

Question 87

Which of the following is least influenced by a project manager, according to the project manager's sphere of influence?

Options:

A.

Sponsors

B.

Project team

C.

Steering committees

D.

Stakeholders

Question 88

An adaptive project team is grooming the backlog for the next iteration. What does the team need to document in the user stories to determine the work needed to complete each story?

Options:

A.

Team velocity in past iterations

B.

Related epics of each story

C.

Product owner's priorities

D.

Detailed acceptance criteria