Question 85

Regression analysis, failure mode and effect analysis (FMEA), fault tree analysis (FTA), and trend analysis are examples of which tool or technique?

Options:

A.

Expert judgment

B.

Forecasting methods

C.

Earned value management

D.

Analytical techniques

Question 86

When paying a consultation fee to a technical expert, what type of contract is often used ' ?

Options:

A.

Time and materials (TandM)

B.

Cost plus incentive fee (CPIF)

C.

Fixed price incentive fee (FPIF)

D.

Cost plus award fee (CPAF)

Question 87

Which of the following schedule network analysis techniques is applied when a critical path method calculation has been completed and resources availability is critical?

Options:

A.

Applying calendars

B.

Resource leveling

C.

Resource planning

D.

Resource conflict management

Question 88

In the Define Activities process, the schedule management plan is used to:

Options:

A.

Capture the lessons learned from other projects for comparison.

B.

Contain the standard activity list.

C.

Document and support the project change requests.

D.

Prescribe the level of detail needed to manage the work.