Question 165

Completion of the product scope is measured against the product:

Options:

A.

prototypes

B.

requirements

C.

analyses

D.

benchmarks

Question 166

Which Develop Schedule tool and technique produces a theoretical early start date and late start date?

Options:

A.

Critical path method

B.

Variance analysis

C.

Schedule compression

D.

Schedule comparison bar charts

Question 167

During project selection, which factor is most important?

Options:

A.

Types of constraints

B.

Internal business needs

C.

Budget

D.

Schedule

Question 168

What describes the relationship between projects, programs, and portfolios?

Options:

A.

Portfolio management focuses on doing the " right " programs and projects.

B.

Project management focuses on doing the " right " programs and portfolios.

C.

Program management focuses on doing the " specific " portfolios and projects.

D.

Portfolio management focuses on doing the ' ' specific’’ programs and projects.