Question 165

Which type of risk diagram is useful for showing time ordering of events?

Options:

A.

Ishikawa

B.

Milestone

C.

Influence

D.

Decision tree

Question 166

Which tool and technique is used in Conduct Procurements?

Options:

A.

Teaming agreements

B.

Expert judgment

C.

Bidder conferences

D.

Contract types

Question 167

The precedence diagramming method (PDM) is also known as:

Options:

A.

Arrow Diagram.

B.

Critical Path Methodology (CPM).

C.

Activity-On-Node (AON).

D.

schedule network diagram.

Question 168

Ensuring that both parties meet contractual obligations and that their own legal rights are protected is a function of:

Options:

A.

Conduct Procurements.

B.

Close Procurements.

C.

Administer Procurements,

D.

Plan Procurements.