Summer Certification Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Passed Exam Today CAPM

Page: 9 / 99
Total 1326 questions

Certified Associate in Project Management (CAPM) Questions and Answers

Question 33

Given the following information.

Activity A takes one week.

Activity B takes three weeks.

Activity C takes two weeks.

Activity D takes five weeks.

Activity A starts at the same time as Activity B.

Activity C follows Activity B and Activity A.

Activity D follows Activity C.

How long will it take to complete the project?

Options:

A.

Eleven weeks

B.

Nine weeks

C.

Eight weeks

D.

Ten weeks

Question 34

Project Stakeholder Management focuses on:

Options:

A.

project staff assignments

B.

project tea m acquisition

C.

managing conflicting interests

D.

communication methods

Question 35

The links between the processes in the Process Groups are often:

Options:

A.

Intuitive

B.

Iterative

C.

Measured

D.

Monitored

Question 36

Which of the following set of items belongs to the communications management plan?

Options:

A.

Escalation processes and meeting management

B.

Project schedule and glossary of common terminology

C.

Escalation processes and stakeholder communication requirements

D.

Interactive communication model and information to be communicated

Page: 9 / 99
Total 1326 questions