Certified Associate in Project Management (CAPM) Questions and Answers

Question 201

Which of the following is an input to Direct and Manage Project Execution?

Options:

A.

Performance reports

B.

Project charter

C.

Outputs from planning processes

D.

Enterprise environmental factors

Question 202

Activity cost estimates are quantitative assessments of the probable costs required to:

Options:

A.

Create WBS.

B.

complete project work.

C.

calculate costs.

D.

Develop Project Management Plan.

Question 203

While preparing the project management plan on a weekly basis, the project manager indicates the intention to provide an issues report to the staff via e-mail. In which part of the plan will this type of information be included?

Options:

A.

Communications management plan

B.

Human resource plan

C.

Quality management plan

D.

Procurement management plan

Question 204

Under which type of contract does the seller receive reimbursement for all allowable costs for performing contract work, as well as a fixed-fee payment calculated as a percentage of the initial estimated project costs?

Options:

A.

Cost Plus Fixed Fee Contract (CPFF)

B.

Cost Plus Incentive Fee Contract (CPIF)

C.

Firm Fixed Price Contract (FFP)

D.

Fixed Price with Economic Price Adjustment Contract (FP-EPA)