Weekend Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

CAPM CAPM Exam Dumps

Page: 33 / 99
Total 1317 questions

Certified Associate in Project Management (CAPM) Questions and Answers

Question 129

Which of the following project documents is an input to the Control Scope process?

Options:

A.

Vendor risk assessment diagram

B.

Risk register

C.

Requirements traceability matrix

D.

Area of responsibility summary

Question 130

In a construction project schedule, what is the logical relationship between the delivery of the concrete materials and the pouring of concrete?

Options:

A.

Start-to-start (SS)

B.

Start-to-finish (SF)

C.

Rnish-to-finish (FF)

D.

Finish-to-start (FS)

Question 131

A method to manage stakeholder expectations in the scope statement is to clearly:

Options:

A.

state the guiding principles of the organization.

B.

identify alternatives to generate different approaches.

C.

state what is out of scope.

D.

outline the results of the Delphi technique.

Question 132

Which of the following events would result in a baseline update?

Options:

A.

A project is behind schedule and the project manager wants the baseline to reflect estimated actual completion.

B.

A customer has approved a change request broadening the project scope and increasing the budget.

C.

One of the risks identified in the risk management plan occurs, resulting in a schedule delay.

D.

One of the key project team resources has left the team and no replacement is available.

Page: 33 / 99
Total 1317 questions