Weekend Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

PMI CAPM Actual Questions

Page: 12 / 100
Total 1250 questions

Certified Associate in Project Management (CAPM) Questions and Answers

Question 45

In Project Cost Management, which input is exclusive to the Determine Budget process?

Options:

A.

Scope baseline

B.

Organizational process assets

C.

Project schedule

D.

Resource calendars

Question 46

What is the schedule performance index (SPI) using the following data? BAC = $100,000 PV = $50,000 AC = $80,000 EV = $40,000

Options:

A.

1

B.

0.4

C.

0.5

D.

0.8

Question 47

In which process is a project manager identified and given the authority to apply resources to project activities?

Options:

A.

Acquire Project Team

B.

Develop Project Management Plan

C.

Manage Project Execution

D.

Develop Project Charter

Question 48

Which of the following Project Communication Management processes uses performance reports as an input?

Options:

A.

Manage Stakeholder Expectations

B.

Report Performance

C.

Distribute Information

D.

Plan Communications

Page: 12 / 100
Total 1250 questions