Weekend Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

PMI CAPM Actual Questions

Page: 12 / 99
Total 1317 questions

Certified Associate in Project Management (CAPM) Questions and Answers

Question 45

Which input to the Identify Stakeholders process provides information about internal or external parties related to the project?

Options:

A.

Procurement documents

B.

Communications plan

C.

Project charter

D.

Stakeholder register

Question 46

Which process identifies whether the needs of a project can best be met by acquiring products, services, or results outside of the organization?

Options:

A.

Plan Procurement Management

B.

Control Procurements

C.

Collect Requirements

D.

Plan Cost Management

Question 47

In a project, total float measures the:

Options:

A.

Ability to shuffle schedule activities to lessen the duration of the project.

B.

Amount of time an activity can be extended or delayed without altering the project finish date.

C.

Cost expended to restore order to the project schedule after crashing the schedule.

D.

Estimate of the total resources needed for the project after performing a forward pass.

Question 48

Which type of dependency is legally or contractually required or inherent in the nature of work and often involves physical limitations?

Options:

A.

Mandatory

B.

Discretionary

C.

Internal

D.

External

Page: 12 / 99
Total 1317 questions