Weekend Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Download Full Version CAPM PMI Exam

Page: 48 / 100
Total 1250 questions

Certified Associate in Project Management (CAPM) Questions and Answers

Question 189

A project manager has to share a status report with a new stakeholder and is trying to determine the level of detail to include in the report. Which document best details the information the project manager needs lo make this decision?

Options:

A.

Organizational process assets

B.

Change management plan

C.

Communications management plan

D.

Resource management plan

Question 190

Which action should the project manager take after the team finishes executing the scope?

Options:

A.

Verify the deliverables to ensure that they are correct and meet the customer's satisfaction.

B.

Accept all the deliverables and deliver them to the customer for final acceptance.

C.

Conduct a joint session with the customer, change the deliverables, and then request approval.

D.

Check that all change requests were implemented and release deliverables to the customer.

Question 191

What can increase the complexity of the Manage Stakeholder Engagement process?

Options:

A.

The project must be of high quality.

B.

The stakeholders are from different countries.

C.

The project must comply with strict local government regulations.

D.

The project has a tight budget and timeline.

Question 192

A project manager Is addressing risks and potential concerns related to stakeholder management, and Is clarifying and resolving previously Identified issues. In which process is the project manager engaged?

Options:

A.

Identify Stakeholders

B.

Plan Stakeholder Engagement

C.

Manage Stakeholder Engagement

D.

Monitor Slakeholder Engagement

Page: 48 / 100
Total 1250 questions