Summer Certification Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Helping Hand Questions for CAPM

Page: 29 / 99
Total 1326 questions

Certified Associate in Project Management (CAPM) Questions and Answers

Question 113

What are the inputs of the Estimate Costs process?

Options:

A.

Project management plan, work performance data, enterprise environmental factors, and organizational process assets

B.

Project management plan, project documents, enterprise environmental factors, and organizational process assets

C.

Cost baseline, enterprise environmental factors, benefits management plan, and organizational process assets

D.

Project management plan, enterprise environmental factors, basis of estimates, and organizational process assets

Question 114

A project manager is developing the work breakdown structure (WBS) for a project. The team is asking at what level should they decompose their assigned work.

What should the project manager answer?

Options:

A.

Activity level

B.

Deliverable level

C.

Task level

D.

Work package level

Question 115

At the start of a typical project life cycle, costs are:

Options:

A.

low, peak as work is carried out, and drop as the project nears the end.

B.

low, become steady as work is carried out, and increase as the project nears the end.

C.

high, drop as work is carried out, and increase as the project nears the end.

D.

high, become low as work is carried out, and drop as the project nears the end.

Question 116

The contract in which the seller is reimbursed for all allowable costs for performing the contract work and then receives a fee based upon achieving certain performance objectives is called a:

Options:

A.

Cost Plus Incentive Fee Contract (CPIF).

B.

Cost Plus Fixed Fee Contract (CPFF).

C.

Fixed Price Incentive Fee Contract (FPIF).

D.

Time and Material Contract (TandM).

Page: 29 / 99
Total 1326 questions