Question 49

Which is an enterprise environmental factor?

Options:

A.

Marketplace conditions

B.

Policies and procedures

C.

Project files from previous projects

D.

Lessons learned from previous projects

Question 50

The degree, amount, or volume of risk that an organization or individual will withstand is called risk:

Options:

A.

appetite

B.

tolerance

C.

threshold

D.

management

Question 51

Success is measured by benefits realization for a:

Options:

A.

strategic plan

B.

project

C.

portfolio

D.

program

Question 52

Through whom do project managers accomplish work?

Options:

A.

Consultants and stakeholders

B.

Stakeholders and functional managers

C.

Project team members and consultants

D.

Project team members and stakeholders