Weekend Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Changed CAPM Exam Questions

Page: 20 / 99
Total 1317 questions

Certified Associate in Project Management (CAPM) Questions and Answers

Question 77

If the estimate at completion (EAC) is 25, and the budget at completion (BAC) is 17, what is the variance at completion (VAC)?

Options:

A.

-8

B.

425

C.

1.4

D.

8

Question 78

A project manager is reporting the project performance as 25 days worth of work completed against 13 days originally planned. What is the schedule variance (SV)?

Options:

A.

-12

B.

1.15

C.

38

D.

12

Question 79

A project manager read the initial contract when a project was started. The contract states a house has to be built in one year, and the foundation has to be completed in 30 days. What should the project manager do?

Options:

A.

Add the milestones to the risk register, as time is short.

B.

Add the two milestones to the project plan, as they are mandatory.

C.

Calculate the duration of the two milestones stated in the contract.

D.

Start the project as soon as possible, as time is short.

Question 80

On which type of project.... only after the final iteration?

On wtiich type of project lite cycle is ihe deliverable produced trough a series of ileralrons considering thai the deliverable ts completed only after the Imal iteration?

Options:

A.

Incremental life cycle

B.

Predictive life cycle

C.

Iterative life cycle

D.

Adaptive life cycle

Page: 20 / 99
Total 1317 questions