If the estimate at completion (EAC) is 25, and the budget at completion (BAC) is 17, what is the variance at completion (VAC)?
A project manager is reporting the project performance as 25 days worth of work completed against 13 days originally planned. What is the schedule variance (SV)?
A project manager read the initial contract when a project was started. The contract states a house has to be built in one year, and the foundation has to be completed in 30 days. What should the project manager do?
On which type of project.... only after the final iteration?
On wtiich type of project lite cycle is ihe deliverable produced trough a series of ileralrons considering thai the deliverable ts completed only after the Imal iteration?