Certified Associate in Project Management (CAPM) Questions and Answers

Question 153

Types of internal failure costs include:

Options:

A.

inspections.

B.

equipment and training.

C.

lost business.

D.

reworking and scrapping.

Question 154

Change request status updates are an output of which process?

Options:

A.

Perform Integrated Change Control

B.

Direct and Manage Project Execution

C.

Close Project or Phase

D.

Monitor and Control Project Work

Question 155

Which type of chart is a graphic representation of a process showing the relationships among process steps?

Options:

A.

Control

B.

Bar

C.

Flow

D.

Pareto

Question 156

Which process involves identifying and documenting the logical relationships between project activities?

Options:

A.

Develop Schedule

B.

Sequence Activities

C.

Create WBS

D.

Applying leads and lags