Question 161

Following the rollout of an enterprise IT software solution that hosts sensitive data it was discovered that the application's role-based access control was not functioning as specified Which of the following is the BEST way to prevent reoccurrence in the future?

Options:

A.

Ensure supplier contracts include penalties if solutions do not meet functional requirements

B.

Ensure the evaluation process requires independent assessment of solutions prior to implementation

C.

Ensure supplier contracts include a provision for the right to audit on an annual basis

D.

Ensure procurement processes require the identification of alternate vendors to ensure business continuity.

Question 162

Which of the following should be the PRIMARY consideration for an enterprise when prioritizing IT projects?

Options:

A.

Technical capability of the enterprise to execute the projects

B.

Process owner expectations based on operational benefits

C.

Results of IT performance benchmarks against competitors

D.

Impact on the business due to expected project outcomes

Question 163

An enterprise's global IT program management office (PMO) has recently discovered that several IT projects are being run within a specific region without knowledge of the PMO. The projects are on time, on budget, and will deliver the proposed benefits to the specific region. Which of the following should be the PRIMARY concern of the PMO?

Options:

A.

Inability to reduce the impact to the risk level of the global portfolio

B.

Projects may not follow system development life cycle (SDLC)

C.

Lack of control and impact to the overall PMO budget

Question 164

To develop appropriate measures to improve organizational performance, the measures MUST be:

Options:

A.

a result of benchmarking and comparative analysis.

B.

accepted by and meaningful to the stakeholders.

C.

based on existing and validated data sources.

D.

approved by the IT steering committee.