Weekend Sale Special - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

USGBC LEED-AP-BD+C Dumps

Page: 1 / 17
Total 232 questions

LEED AP Building Design + Construction (LEED AP BD+C) Questions and Answers

Question 1

Which of the following project team members should be integrated early into the design phase to assist with earning the Materials and Resources Prerequisite, Construction and Demolition Waste Management Planning?

Options:

A.

Owner

B.

Contractor

C.

Occupants

D.

Facility manager

Question 2

Who must be a member of the integrated project team for the Integrative Process Prerequisite, Integrative ProjectPlanning and Design?

Options:

A.

The general contractor

B.

A LEED AP

C.

The project's mechanical engineer

D.

The owner or an owner's representative

Question 3

A building owner in an arid climate is trying to design an outdoor lunch area for the tenants. Which landscaping

strategy is important to employ in order to reduce water demand?

Options:

A.

Large maple trees for shading

B.

Xeriscaping landscape beds

C.

Turf grass area for picnic benches

D.

Tropical flowers next to park benches

Question 4

A project team is using the whole building simulation model to quantify the percentage of energy savings for the project. Which of the following should remain the same for both the baseline building and the proposed building?

Options:

A.

Building operating schedule and occupancy hours

B.

Building operating schedule and total window area

C.

Building envelope construction and occupancy hours

D.

Total window area and building envelope construction

Question 5

The material cost for a project is $100,000. What is the minimum material value needed to achieve Materials and Resources Credit, Building Disclosure and Optimization, Sourcing of Raw Materials, Option 2. Leadership Extraction

Practices?

Options:

A.

$10,000

B.

$12,500

C.

$22,500

D.

$25,000

Question 6

What is the average flush rate for a dual flush toilet with a high flush rate of 1.6 gpf (6 lpf) and a low flush rate of 1.05 gpf (4 lpf)?

Options:

A.

1.05 gpf (4 lpf)

B.

1.19 gpf (4.5 lpf)

C.

1.23 gpf (4.66 lpf)

D.

1.32 gpf (5 lpf)

Question 7

A new commercial building is being designed to use small capacity air handling units. To meet the requirements of the Carbon Dioxide Monitoring strategy in the Indoor Environmental Quality Credit, Enhanced Indoor Environmental

Quality Strategies, where would CO2 monitors need to be located?

Options:

A.

In each occupied space

B.

In each densely occupied space

C.

In each occupied space and outdoors

D.

In each occupied space over 500 ft2 (46 m2)

Question 8

A comprehensive rainwater management plan may include design elements such as

Options:

A.

artificial turf, bioretention pond, cisterns and hay bales

B.

cisterns, porous pavement, swales and vegetated roofs

C.

soil compaction, swales, vegetated roofs and xeriscaping

D.

bioretention pond, cisterns, porous pavement and stabilized construction entrance

Question 9

When using the Integrative Process, what is the best way for the LEED AP to assess the impact of indoor and outdoor water consumption in a Building Design and Construction project?

Options:

A.

Perform a preliminary water budget analysis before the completion of schematic design

B.

Install permanent metering on both the water sources and the waste water leaving the site

C.

At the completion of schematic design, count the fixtures and apply the maximum flow rate

D.

Estimate consumption by using 20 gal. per day (76 I per day) for each Full Time Equivalent (FTE) scheduled to occupy the building

Question 10

A project team seeking certification for a new school is attempting to achieve Materials and Resources Credit, Construction and Demolition Waste Management, Option 2. Reduction of Total Waste Material. What strategy can be taken to meet the requirements of this credit?

Options:

A.

Track waste materials per occupant

B.

Track waste materials used on site

C.

Document total waste by project cost

D.

Document total waste per building floor area

Question 11

Which of the following could be considered diverted construction waste?

Options:

A.

Excavated soil

B.

Land-clearing debris

C.

Alternative daily cover

D.

Asphalt with aggregate

Question 12

Which of the following is an example of a nonroof measure for Sustainable Sites Credit, Heat Island Reduction?

Options:

A.

A playground with artificial turf

B.

A vegetated shading structure

C.

A shade structure with a three-year aged Solar Reflectance Index (SRI) value of 0.2

D.

A paving material with a three-year aged SRI value of 0.2

Question 13

A project is designed to remodel an existing warehouse into multi-family housing. The exterior facade of the warehouse will remain, but 40% of the interior will be demolished and replaced for interior new construction. New materials will be used for the new construction. To achieve points in the Materials and Resources Credit, Building Life-Cycle Impact Reduction, which credit path option would apply?

Options:

A.

Historic Building Reuse

B.

Building and Material Reuse

C.

Whole-Building Life-Cycle Assessment

D.

Renovation of Abandoned or Blighted Building

Question 14

Which is a benefit of earning Regional Priority credits?

Options:

A.

The LEED project can achieve more sustainable outcomes by recognizing the issues that are a priority in the project's location

B.

The context of the project's location is not addressed, allowing the project team to focus on the building's priority issues

C.

The project's operations are considered separately from design and construction, allowing the project team to focus on regional issues

D.

The LEED project is able to skip a review phase by considering the issues that are a priority in the project's location

Question 15

The intent of the Sustainable Sites Prerequisite. Construction Activity Pollution Prevention is to £

Options:

A.

control erosion, noxious odors and landfill waste

B.

control erosion, landfill waste and excessive noise

C.

control erosion, waterway sedimentation and airborne dust

D.

control erosion, waterway sedimentation and noxious odors

Question 16

The total land area within a 1/4 mi. (0.40 km) radius of a project boundary consists of 130 acres (53 hectares) andhas a residential to nonresidential ratio of 60:40. Within this same total land area, there are 780 dwelling units and1,600,000 ft2 (148 645 m2) of nonresidential building space. Given these parameters, what are the surroundingresidential and nonresidential densities when attempting to achieve Location and Transportation Credit,Surrounding Density and Diverse Uses?

Options:

A.

10 dwelling units per acre (24 dwelling units per hectare) and a Floor Area Ratio (FAR) of 0.47

B.

10 dwelling units per acre (24 dwelling units per hectare) and a FAR of 0.70

C.

13 dwelling units per acre (32 dwelling units per hectare) and a FAR of 0.47

D.

15 dwelling units per acre (36 dwelling units per hectare) and a FAR of 0.70

Question 17

The use of lead, mercury, copper and cadmium should be limited because they all

Options:

A.

are persistent bioaccumulative toxins

B.

reduce the life cycle assessment of a building

C.

take an unreasonable amount of energy to recycle

D.

interfere with the magnetic instruments in a medical building

Question 18

Which of the following statements is correct when defining the project boundary?

Options:

A.

The LEED project boundary cannot include non-contiguous land

B.

The LEED project boundary cannot include more than one building

C.

The land associated with the project supports typical operation

D.

The gross floor area of the LEED project should be no less than 1% of the gross land area within the LEED project boundary

Question 19

A project attempting to meet the preferred parking requirements for Location and Transportation Credit, Green Vehicles may provide what incentive to meet the requirements and highlight the project sustainable vehicle strategy?

Options:

A.

Three years of free parking for green vehicles

B.

Preferred parking decals for 5% of occupants utilizing carpool vehicles

C.

A permanent discounted parking rate of at least 20% for all green vehicles

D.

An annual maintenance voucher for at least 5% of occupants driving green vehicles

Question 20

According to the Integrative Process Credit, the discovery phase of energy-related systems should identify

Options:

A.

ventilation rates

B.

functional performance tests

C.

thermal comfort ranges

D.

transportation options

Question 21

When preparing the Sustainable Sites Prerequisite, Construction Activity Pollution Prevention, the ConstructionGeneral Permit must contain which of the following?

Options:

A.

Waste Management Plan

B.

Building orientation on the site

C.

Installation plan for perimeter control

D.

Minimum standards for equipment exhaust

Question 22

A project has total waste of 20 tons (18.1 tonnes) that includes the following:

· 8 tons (7.3 tonnes) of recycled demolition steel and concrete

· 2 tons (1.8 tonnes) of trees cleared from the site

. 3 tons (2.7 tonnes) of commingled scrap with 40% diverted

. 6 tons (5.4 tonnes) of used furniture donated to a non-profit organization

· 1 ton (0.9 tonnes) of removed carpet and ceiling tiles sent back to the manufacturer

What is the percentage of diverted waste for Materials and Resources Credit, Construction and Demolition Waste

Management?

Options:

A.

60%

B.

75%

C.

90%

D.

100%

Question 23

In addition to Materials and Resources Credit, Building Life-Cycle Impact Reduction, Option 3. Building and Materials Reuse, salvaged materials contribute to the achievement of

Options:

A.

Materials and Resources Prerequisite, Storage and Collection of Recyclables

B.

Materials and Resources Credit, Building Product Disclosure and Optimization - Material Ingredients

C.

Materials and Resources Credit, Construction and Demolition Waste Management

D.

Materials and Resources Credit, Building Product Disclosure and Optimization - Environmental Product Declarations

Question 24

A tenant of a new office building will require 100 workstations per floor. Each floor will have two bathroom facilities and one conference room. How many lighting control devices with at least three lighting levels per floor are required to comply with Indoor Environmental Quality Credit, Interior Lighting, Option 1. Lighting Control?

Options:

A.

91 lighting control devices

B.

93 lighting control devices

C.

100 lighting control devices

D.

103 lighting control devices

Question 25

Which of the following strategies is allowed under Energy Atmosphere Credit, Renewable Energy Production, and will help a project achieve Energy Atmosphere Credit, Optimize Energy Performance?

Options:

A.

Install an on-site photovoltaic array

B.

Purchase Green-e certified carbon offsets

C.

Purchase Green-e certified Renewable Energy Certificates (RECs)

D.

Install a ground-source heat pump

Question 26

A design team is working on a new building project and is employing an integrated, whole-building approach. Thearchitects want to increase the size of a glazed opening on the south facing wall. Which team members are first

affected by this change?

Options:

A.

Civil engineers

B.

Facility managers

C.

Landscape architects

D.

Mechanical engineers

Question 27

When working on a renovation project, asbestos containing materials have been found on the perimeter walls. When calculating the percentage of building being reused under the Materials and Resources Credit, Building Life-Cycle Impact Reduction, the materials remediated will be

Options:

A.

included in the calculation

B.

excluded from the calculation

C.

excluded if the total volume is less than 25% of the building being reused

D.

excluded if the total volume is more than 25% of the building being reused

Question 28

Which of the following is true regarding LEED Pilot Credits?

Options:

A.

Pilot Credits are not specific to the rating systems

B.

Pilot Credits can be attempted in the design review stage only

C.

A registered Pilot Credit must be replaced on the LEED project's scorecard if that pilot credit is removed from the Pilot Credit Library

D.

Pilot Credit feedback surveys must be completed

Question 29

A design team is pursuing Indoor Environmental Quality Credit, Indoor Air Quality Assessment. The building is 1,000 ft2 (93 m2) and has a 10 ft. (3 m) ceiling height. In order to earn the credit, what is the required volume of

supply air for the entire building flush-out?

Options:

A.

3,500,000 ft3 (99 108 m3)

B.

10,000,000 ft3 (283 168 m3)

C.

14,000,000 ft3 (396 435 m3)

D.

35,000,000 ft3 (991 089 m3)

Question 30

Which of the following contributes to the value of the commissioning process?

Options:

A.

Ensuring that the project budgetary goal is met

B.

Verifying that the building systems perform as intended

C.

Verifying that the building water fixtures are installed properly

D.

Ensuring that the project is delivered to meet the permitting requirements

Question 31

A project team is deciding on the impact of a proposed concrete walkway. Which of the following will be impacted as a result of adding the walkway?

Options:

A.

Site's impervious cover

B.

Project density calculations

C.

Erosion and sediment control plan during construction

D.

Air quality as a result of off gassing that occurs as concrete cures

Question 32

A project design team for an elementary school project is attempting to achieve Innovation Credit, Innovation, Option 1. Innovation. Which of the following strategies would qualify?

Options:

A.

Pilot Credit from LEED Pilot Credit Library

B.

Exemplary Performance in Energy and Atmosphere Credit, Optimize Energy Performance

C.

Create educational kiosks and posters around the school with picture of building systems'sustainable features

D.

Implement a building as a learning lab curriculum that has been piloted in three other primary schools in the district

Question 33

Plug-in task lighting will be utilized in a LEED project at all workstations. The task lighting is not included in the installed lighting power calculations for Energy and Atmosphere Prerequisite, Minimum Energy Performance since

Options:

A.

it is being covered by Indoor Environmental Quality Credit, Interior Lighting, Option 1. Lighting Control

B.

it is specifically exempted by ASHRAE

C.

it will be installed by the owner

D.

the lamp wattage has not been determined

Question 34

A project team has installed a rainwater harvesting system on site. In which of the following could this system be recognized?

Options:

A.

Water Efficiency Credit, Water Metering and Water Efficiency Prerequisite, Indoor Water Use Reduction

B.

Water Efficiency Credit, Water Metering and Water Efficiency Prerequisite, Outdoor Water Use Reduction

C.

Sustainable Sites Credit, Rainwater Management and Water Efficiency Credit, Indoor Water Use Reduction

D.

Sustainable Sites Credit, Rainwater Management and Water Efficiency Prerequisite, Indoor Water Use Reduction

Question 35

Which of the following standards needs to be followed to comply with Indoor Environmental Quality Credit, Thermal Comfort?

Options:

A.

ASHRAE 55-2010

B.

ASHRAE 62.1-2010

C.

ASHRAE 90.1-2010

D.

ASHRAE 189.1-2010

Question 36

A commercial new construction project consists of mixed space usage. When deciding which LEED rating system to use, the LEED AP should follow which of the following rules?

Options:

A.

If a rating system is appropriate for less than 50% of the gross area of the LEED project space then the rating system must not be used

B.

If a rating system is appropriate for more than 50% of the gross floor area of LEED project space, then that rating system must be used

C.

If a rating system is appropriate for 30% to 60% of the gross floor area, the project team must independently assess their situation and decide which rating system is most applicable

D.

If a rating system is appropriate for 40% to 60% of the gross floor area, the project team must independently assess their situation and decide which rating system is most applicable

Question 37

A new athletic facility contains a laundry room which is adjacent to the locker rooms. Whichstrategy will contribute

toward the Interior Cross-Contamination Prevention strategy in Indoor Environmental Quality Credit, Enhanced Indoor

Air Quality Strategies?

Options:

A.

Relocate the laundry facility to the basement

B.

Naturally ventilate the laundry space per ASHRAE 62.1-2010

C.

Install particle filters, with a MERV of 13 or higher or F7

D.

Provide a ventilation system specifically for the laundry facility that has no recirculating air

Question 38

Which rating system is being used if all of the credits below have been submitted towards certification?

- Location and Transportation Credit, Reduced Parking Footprint

- Energy and Atmosphere Credit, Fundamental Refrigerant Management

- Indoor Environmental Quality Credit, Acoustic Performance

- Materials and Resources Credit, Persistent, Bio accumulative, and Toxic (PBT) Source Reduction - Lead,Cadmium, and Copper

Options:

A.

Building Design and Construction: Schools

B.

Building Design and Construction: Healthcare

C.

Building Design and Construction: Hospitality

D.

Building Design and Construction: Data Centers

Question 39

An HVAC system consists of an air handler supplying conditioned air (mixture of return air andoutdoor air) to anoffice, corridor, conference room and lobby. For Indoor Environmental Quality Prerequisite, Minimum Indoor AirQuality Performance, the ventilation rate procedure calculations must be based upon what HVAC systemconfiguration?

Options:

A.

Single-zone system

B.

Multiple-zone system

C.

Mixed-mode system

D.

100% outdoor air system

Question 40

A project elects to pursue Location and Transportation Credit, Surrounding Density and Diverse Uses, Option 2. Diverse Uses because of the project's location in an amenity-rich area. The project features 18 uses overall, including at least four uses in three of the five use type categories. What threshold must the project surpass in order to demonstrate exemplary performance for Option 2?

Options:

A.

Exemplary Performance is not available for Option 2

B.

15 uses, including two uses in each of the five categories

C.

15 uses, including at least one Food Retail and one Community Anchor use

D.

18 uses, including uses in at least four of the five use type categories

Question 41

During preliminary energy analysis, what energy reduction strategies can best help in reducing the energy load in the new building construction project?

Options:

A.

Green roof

B.

Site conditions

C.

Massing and orientation

D.

Programmatic and operational parameters

Question 42

Which item is included in the reuse calculation for Materials and Resources Credit, Building Life-Cycle Impact Reduction?

Options:

A.

Floor decking

B.

Asbestos insulation

C.

Exterior glazing

D.

Plumbing fixtures

Question 43

For Energy and Atmosphere Credit, Advanced Energy Metering, what is the minimum amount of time that the metering system should store data?

Options:

A.

6 months

B.

12 months

C.

24 months

D.

36 months

Question 44

A LEED AP submitted a Preliminary Design and Construction review and has received a review comment and technical advice on Materials and Resources Prerequisite, Construction and Demolition Waste Management Planning. Which of the following actions should the LEED AP do if the project continues to pursue LEED certification?

Options:

A.

Revise the documentation and resubmit the form

B.

Abandon meeting this prerequisite

C.

Submit an appeal to Green Business Certification Inc.

D.

Ask the General Contractor to be more aggressive with recycling goals

Question 45

Which federal agency designates Federal Renewal Community sites, which can be considered High Priority Sites for

project development?

Options:

A.

U.S. Internal Revenue Service

B.

U.S. Department of Agriculture

C.

U.S. Environmental Protection Agency

D.

U.S. Department of Housing and Urban Development

Question 46

The Solar Reflectance Index (SRI) includes the measure of a material's

Options:

A.

color (shade of gray)

B.

ability to reflect solar radiation

C.

ability to absorb solar radiation

D.

ability to reflect thermal radiation

Question 47

A building owner is considering the installation of a solar thermal panel on the roof of the building. The initial cost of the system is higher than a conventional natural gas system. Which of the following is true to make the renewable energy option economically feasible?

Options:

A.

Utility cost savings over the lifetime of the system must offset the higher initial cost

B.

Higher initial cost must exceed the cost of the utility over the lifetime of the system

C.

Higher initial cost must exceed the savings on the utility cost over the lifetime of the system

D.

Utility cost savings over the lifetime of the system must be lower than the higher initial cost of the system

Question 48

What document allows a LEED AP to register a project and sign the Certification Agreement?

Options:

A.

Owner Confirmation of Agent Authority

B.

Architect Code of Professional Conduct

C.

Commissioning (Cx) Agent Construction Permit

D.

LEED AP Standard Form of Agreement Between Owner and Architect

Question 49

Which of the following should be analyzed when pursuing an Integrative Design Process focusing on Energy-Related

Systems?

Options:

A.

Site conditions

B.

Potable water availability

C.

Acoustic performance of the project

D.

Applicability of Green Vehicles to the project

Question 50

A project team wants to educate the facility manager on the installed building systems to improve Indoor Environmental Quality. They want the facility manager to maintain the systems so that they will continue to function as intended. Which of the following should be provided to the facility manager?

Options:

A.

Vendor invoices for mechanical equipment

B.

Preventive maintenance plan for the building

C.

As-built drawings and copies of material submittals

D.

A copy of the credit documentation for the credits that were approved by Green Business Certification Inc. (GBCI)

Question 51

A project team compares a life-cycle assessment (LCA) model to a baseline design to determine the reductions in six impact categories. One impact category exceeds the baseline by 7%. Whichalternative analyses should the team run to check different impact measurements?

Options:

A.

Change the orientation of the design case building

B.

Optimize the slab depth of the design case building

C.

Decrease the gross floor area of the baseline building

D.

Increase the wall mass and types of windows in the baseline building

Question 52

Which of the following products are eligible for a WaterSense label?

Options:

A.

Tankless toilets

B.

Waterless urinals

C.

Public lavatory faucets

D.

Private lavatory faucets

Question 53

For major renovation and new construction projects, the required energy and water-related system analyses should be the same except for

Options:

A.

site conditions

B.

massing and orientation

C.

plug and process load needs

D.

building envelope performance

Question 54

What is the definition of the evapotranspiration rate?

Options:

A.

Evaporation of onsite reuse water

B.

Percentage of potable water usage for irrigation

C.

Water loss from evaporation in micro irrigation systems

D.

Amount of water loss in a vegetated surface in units of water depth

Question 55

Which of the following Water Efficiency credits differ between LEED Building Design and Construction: New Construction and LEED Building Design and Construction: Healthcare?

Options:

A.

LEED Building Design and Construction: Healthcare has no Water Efficiency Credit, Cooling Tower Water Use

B.

LEED Building Design and Construction: New Construction has no Water Efficiency Credit, Cooling Tower Water Use

C.

LEED Building Design and Construction: Healthcare has additional appliance and process water requirements in Water Efficiency Prerequisite, Indoor Water Use Reduction

D.

LEED Building Design and Construction: New Construction has additional appliance and process water requirements in Water Efficiency Prerequisite, Indoor Water Use Reduction

Question 56

A commercial office building with a footprint of 70,000 ft2 (6 503.2 m2) has an overall site area of 200,000 ft2 (18 580.6

m2). The project design includes 15,000 ft2 (1 393.5 m2) of pedestrian oriented hardscape and 18,000 ft2 (1 672.3 m2)

of vegetated open space. Which of the following is necessary to satisfy the requirement for the outdoor space to be

physically accessible when calculating the Sustainable Sites Credit, Open Space?

Options:

A.

A garden space dedicated to industrial food production for use by local communities

B.

A garden space with only one vegetation type and species during the summer for visual interest

C.

A dark paving area with site elements to encourage parking near wetlands or naturally designed ponds

D.

A pedestrian-oriented paving or turf area with physical site elements that accommodate outdoor social activities

Question 57

The LEED AP is leading the first design charrette for a new LEED project with the project's owners. What document

should be used to record the project goals to be used throughout the design of the project?

Options:

A.

Owner's Project Requirements (OPR)

B.

Owner's list of wants and needs

C.

Criteria for contractor selection

D.

Basis of Design (BOD)

Question 58

Building Product Disclosure and Optimization is based on market

Options:

A.

reliability

B.

durability

C.

transparency

D.

consumption

Question 59

A LEED AP is evaluating whether Indoor Environmental Quality Credit, Acoustic Performance is feasible for a LEED

AP Building Design and Construction: Healthcare project. Which of the following groups of documents would best inform this decision?

Options:

A.

Airport flyover maps, mechanical plans, wall sections

B.

Patient records, wall sections, ceiling panel cut sheets

C.

Occupancy statistics, patient records, MRI machine specifications

D.

MRI machine specifications, mechanical plans, occupancy statistics

Question 60

Qualifying spaces for the Sustainable Sites Credit. Places of Respite must tgj

Options:

A.

be located outdoors near a water feature

B.

be located at least 20 ft. (6 m) from a smoking area

C.

have provisions for direct medical care to be delivered in the area

D.

have options for shade or indirect sun for a portion of seating spaces

Question 61

Green Infrastructure (GI) and Low-Impact Development (LID) rainwater management strategies improve upon the

conventional approach for rainwater management by

Options:

A.

replicating a site's natural hydrology

B.

discharging rainwater at a faster rate

C.

increasing a site's impervious surface

D.

providing a greater volume of rainwater detention

Question 62

U.S. Green Building Council (USGBC)'s vision for using LEED internationally includes

Options:

A.

allowing more stringent credit requirements for countries outside of the U.S. so that all projects can achieve LEED

B.

creating multiple LEED rating systems for different countries

C.

modifying U.S. reference standards, such as ASHRAE 90.1, to be more appropriate for regions outside the U.S.

D.

providing opportunities for alternative compliance paths that meet the unique needs of a particular region

Question 63

According to the Integrative Process Credit, Integrative Process, the goal-setting workshop should identify

Options:

A.

potential project sites

B.

targeted LEED credits

C.

expected water demand

D.

expected energy demand

Question 64

During a review of the HVAC equipment submittal, the Commissioning Authority (CxA) determined that the contractorsubstituted a higher efficiency piece of equipment. Which of the following is the priority for the CxA to consider?

Options:

A.

Energy meter location

B.

Equipment Maintenance Plan

C.

Owner's Project Requirements

D.

Coordination of other contractors

Question 65

A new school with a 20 car parking lot has set aside four preferred parking spaces for green vehicles. What else must the project team provide to achieve Location and Transportation Credit, Green Vehicles?

Options:

A.

Nothing; the project team has met the credit requirements

B.

Provide secure bike racks for 5% of the building occupants

C.

Provide an additional parking space for a low-emitting and fuel-efficient vehicle

D.

Provide qualifying electrical vehicle supply equipment in 2% of all parking spaces

Question 66

Which views would qualify as a quality view for Indoor Environmental Quality Credit, Quality Views?

Options:

A.

A, B, C

B.

B, C, D

C.

C, D, E

D.

A, B, D

Question 67

What credit rewards customers who change their normal consumption patterns in response to the varying price of energy over time?

  • Energy and Atmosphere Credit, Demand Response

  • Energy and Atmosphere Credit, Advanced Energy Metering

  • Energy and Atmosphere Credit, Building Level Energy Metering

Options:

A.

Energy and Atmosphere Credit, Green Power and Carbon Offsets

Question 68

Which of the following documents contains the design team's interpretation of the Owner's Project Requirements?

Options:

A.

Basis of Design (BOD)

B.

Simple Box Energy Model Analysis

C.

System's manual

D.

Integrated Project Delivery report

Question 69

Which of the following are control measures recommended by the Sheet Metal and Air Conditioning National Contractors Association (SMACNA) for the Indoor Environmental Quality Credit, Construction Indoor Air Quality Management Plan?

Options:

A.

Source control

B.

Material selection

C.

Contractor training

D.

Pre-construction meeting

Page: 1 / 17
Total 232 questions