Question 117

What percentage of all energy usage is attributable to buildings?

Options:

A.

60%

B.

30%

C.

40%

D.

50%

Question 118

Which of the following projects is eligible to pursue the Energy and Atmosphere Prerequisite, Minimum Energy Performance, Option 2. Prescriptive Compliance: ASHRAE 50% Advanced Energy Design Guide?

Options:

A.

50,000 ft2 (4 645 m2) office project

B.

80,000 ft2 (7 432 m2) hospital project

C.

110,000 ft2 (10 219 m2) school project

D.

140,000 ft2 (13 006 m2) retail project

Question 119

The design team is attempting to achieve the Increased Ventilation strategy in the Indoor Environmental Quality Credit, Enhanced Indoor Air Quality in a conference room. The associated ASHRAE standard requires 400 CFM (11.3 CMM) of ventilation air, but the local code requires 500 CFM (14.1 CMM) of ventilation air. What is the required minimum amount of ventilation air to achieve this credit?

Options:

A.

650 CFM (18.4 CMM)

B.

500 CFM (14.1 CMM)

C.

400 CFM (11.3 CMM)

D.

520 CFM (14.7 CMM)

Question 120

Which of the following documents contains the design team's interpretation of the Owner's Project Requirements?

Options:

A.

Basis of Design (BOD)

B.

Simple Box Energy Model Analysis

C.

System's manual

D.

Integrated Project Delivery report