Question 101

A contractor wants to use an adhesive that exceeds the allowed Volatile Organic Compound (VOC) content limit under Indoor Environmental Quality Credit, Low Emitting Materials. This credit can be earned if

Options:

A.

the VOC budget method is applied for VOC content

B.

the adhesive is not included in the LEED documentation

C.

75% of the adhesives used comply with the VOC content limit and emissions requirements

D.

95% of the adhesives used comply with the VOC content limit and emissions requirements

Question 102

What building classification requires the energy model to determine the predicted power usage effectiveness (PUE) for Energy and Atmosphere Prerequisite, Minimum Energy Performance?

Options:

A.

Office

B.

Hospital

C.

Warehouse

D.

Data Center

Question 103

During a review of the HVAC equipment submittal, the Commissioning Authority (CxA) determined that the contractor substituted a higher efficiency piece of equipment. Which of the following is the priority for the CxA to consider?

Options:

A.

Energy meter location

B.

Equipment Maintenance Plan

C.

Owner's Project Requirements

D.

Coordination of other contractors

Question 104

To achieve the Sustainable Sites Credit, Light Pollution Reduction, Option 1. BUG Rating Method, projects must demonstrate

Options:

A.

all luminaires have full cutoff fixtures

B.

all luminaires have a minimum color temperature of 3500 K

C.

all luminaires meet acceptable fixture ratings for the project's Model Lighting Ordnance (MLO) lighting zone

D.