Question 105

Which site preparation and construction method contributes to earning the Materials and Resources Credit, Construction and Demolition Waste Management?

Options:

A.

Reuse excavated soil and land-clearing debris

B.

Implement in situ soil remediation and post removal of the existing concrete pavement

C.

Salvage and recycle 50% of the existing materials (based on volume) generated during site demolition for three material streams

D.

Ensure reduction of pollution from construction activities by using airborne dust generation capture systems

Question 106

When working on a renovation project, asbestos containing materials have been found on the perimeter walls. When calculating the percentage of building being reused under the Materials and Resources Credit, Building Life-Cycle Impact Reduction, the materials remediated will be

Options:

A.

included in the calculation

B.

excluded from the calculation

C.

excluded if the total volume is less than 25% of the building being reused

D.

excluded if the total volume is more than 25% of the building being reused

Question 107

The LEED AP is leading the first design charrette for a new LEED project with the project's owners. What document should be used to record the project goals to be used throughout the design of the project?

Options:

A.

Owner's Project Requirements (OPR)

B.

Owner's list of wants and needs

C.

Criteria for contractor selection

D.

Basis of Design (BOD)

Question 108

A decorative overhead light fixture is specified for a project that costs $1,500 USD and uses recycled water bottles as part of the diffuser shade. The shades are 10% of the overall weight of the fixture and are 50% post-consumer recycled content. Assuming no other portions of the fixture meet sustainability criteria, what would the contributing value of the fixture be?

Options:

A.

$75

B.

$150

C.

$750

D.

$1,500