Question 25

A project will renovate a building with historic designation into new office space. The surface area of the existing building structure and envelope is 100,000 ft² (9,290 m²). How much of the existing building will need to be reused to earn 5 points for the Materials and Resource Credit, Building Life-Cycle Impact Reduction?

Options:

A.

90,000 ft² (8,361 m²)

B.

There is no minimum

C.

80,000 ft² (7,432 m²)

D.

At least 50% of the surface area

Question 26

What percentile of runoff from a regional development of an office building must a project manage on site by using low-impact development and green infrastructure to achieve three points under the Sustainable Sites Credit-Rainwater Management, Option 1. Percentile of Rainfall Events?

Options:

A.

98th percentile

B.

85th percentile

C.

95th percentile

D.

100th percentile

Question 27

Major renovation projects must meet which of the following minimum percentage savings when taking credit for renewable energy systems?

Options:

A.

5%

B.

3%

C.

2%

D.

8%

Question 28

Which of the following statements are true for Erosion and Sedimentation Control (ESC) plan prerequisite compliance?

Options:

A.

The ESC plan cannot be modified during the design phase of the LEED certification

B.

The ESC plan can be developed or modified during the design phase of LEED certification

C.

A compliant ESC plan may be developed during construction

D.

A compliant ESC plan must be in place when the commissioning authority is appointed