PMI PMI-ACP

PMI-ACP: PMI Agile Exam 2025 Study Guide Pdf and Test Engine

Are you worried about passing the PMI PMI-ACP (PMI Agile Certified Practitioner (PMI-ACP)) exam? Download the most recent PMI PMI-ACP braindumps with answers that are 100% real. After downloading the PMI PMI-ACP exam dumps training , you can receive 99 days of free updates, making this website one of the best options to save additional money. In order to help you prepare for the PMI PMI-ACP exam questions and verified answers by IT certified experts, CertsTopics has put together a complete collection of dumps questions and answers. To help you prepare and pass the PMI PMI-ACP exam on your first attempt, we have compiled actual exam questions and their answers. 

Our (PMI Agile Certified Practitioner (PMI-ACP)) Study Materials are designed to meet the needs of thousands of candidates globally. A free sample of the CompTIA PMI-ACP test is available at CertsTopics. Before purchasing it, you can also see the PMI PMI-ACP practice exam demo.

PMI Agile Certified Practitioner (PMI-ACP) Questions and Answers

Question 1

What information should a project team include in an extended stakeholder report to ensure that all current and future stakeholders are aware of the frequent updates?

Options:

A.

Team capacity and competence profiles

B.

A list of tools used for implementation

C.

A list of open technical issues

D.

Up-to-date project radiators

Buy Now
Question 2

Options:

A.

Keep sprints short.

B.

Invite the stakeholder to the daily stand-ups.

C.

Ask the stakeholder for estimates for each user story.

D.

Schedule more demos during each sprint.

Question 3

A team worked with a customer to estimate all user stories for the must have features. During release planning sessions, the customer indicated they prefer 3-week iterations that begin on Thursdays and end on Wednesdays. The team spent several days determining which stories should be developed for iteration 0 and understanding the customer’s priorities for the remaining stories. The project sponsor attends the Friday meeting and requests a high-level estimate of when they can invite the chief executive officer (CEO) to a demonstration of the minimum viable product (MVP).

What should the team tell the sponsor at this point in the planning process?

Options:

A.

They do not have enough information to estimate a date range yet but can provide the number of 3-week iterations required.

B.

They can provide an anticipated date with the assumption that conditions will be ideal.

C.

They can provide a broad range but cannot realistically set a target release date until the team's velocity stabilizes.

D.

They will send an update when all of the stories are estimated and prioritized in the backlog.