The high-level technical requirements for a new application state that the application should be suitable to support enterprise-level client-server solutions. Which of the following meets these requirements?
An external developer working on a project at an hourly rate provides an invoice at the end of a month for 80 hours spent on a project. The project manager realizes that there were no tasks assigned to this developer last month. Which of the following actions should the project manager take first?
Which of the following best describes the meaning of timeboxing in the context of a project kickoff meeting?
Which of the following factors would be impacted the most by requirements for a project to implement an air quality control system at a coal plant?
A project manager has decided to outsource portions of a project and will conduct a separate procurement. In which of the following phases does this task occur?
A PM wants to add a chart to the monthly status report to show major accomplishments for key events. Which of the following is the best chart to use?
After new capabilities were deployed in a system, issues with preexisting capabilities were reported. Which of the following testing cycles should be used to prevent this issue?
Which of the following communication methods would be the most appropriate to finalize the handoff of deliverables?
During schedule planning, a project manager determined the logical dependencies required to complete the project. Which of the following activities should the project manager do next?
Given the following chart showing committed work (orange) vs. actual work completed (blue) across 10 sprints:

Which of the following best describes the team ' s performance?
A project manager is managing a virtual team across the country. As reported in the retrospective, the team morale has decreased due to additional production issues. Which of the following meeting tools is the best option to record results in the retrospective?
A project manager is in the closing phase of an IT asset refresh project that involves the disposal of several computers. The project sponsor notified the project manager that the company recently received a penalty as a result of disposing of some computers improperly. Which of the following should have been considered during initial planning to prevent this situation?
A principle states 80% of the issues are the result of 20% of the causes. Which of the following types of diagrams is based on this principle?
Which of the following should occur first when planning maintenance windows?
A demo presentation for a global project was not as successful as expected because the development team misinterpreted which features needed to be incorporated. Which of the
following has the project manager identified?
A company needs to have structured cabling installed in one of its buildings. Which of the following would be the best document for the company to use to obtain and compare information on cabling services and costs from various vendors?
Two developers are discussing the design solution for a particular feature. The meeting is taking longer than expected, and the parties have been unable to reach an agreement. The project manager decides to take a break and continue the meeting on another day. Which of the following techniques is the project manager using?
A project team participates in a brainstorming session to define the guidance, direction, and approach for monitoring established procedures for developed products. Which of the following plans is the team creating?
A project manager buys an extended warranty for a set of servers. Which of the following risk management strategies is the manager using?
Two stakeholders, who have a history of animosity toward one another, are in disagreement during a project. The project ' s timeline depends on the stakeholders accomplishing their tasks. Which of the following conflict resolution methods would be best to utilize?
A project manager operating within a functional organizational structure is trying to avoid a project roadblock due to a mobilization fee that has not been paid to a contractor. Which of the following should the project manager do first?
A project manager is reviewing sprint performance in a retrospective meeting.

Given the following chart, which of the following sprints shows the highest velocity?
Which of the following best describes the reason a chat messaging service would be used as the primary form of communication for a project team?
A project manager was concerned the results were not fulfilling the expectations at the end of the execution phase. After reviewing the SOW, the project manager realized the vendor delivered everything included in the contract. Which of the following actions should the project manager complete next?
A project manager is monitoring team performance by comparing committed versus completed work. The project manager creates the following:

Which of the following most likely represents the number of items in the backlog?
A project team is defining operational training, discussing a go-live date, and describing the operational handoff. Which of the following best describes what the team is developing?
Which of the following requires the MOST availability from the business team?
A project scheduler updates the project status with the following information: SPI = 1.25 and CPI = 0.85. Which of the following can the project manager infer about the current project status?
A critical business initiative introduced new processes and technology to the organization. Which of the following approaches should be used to ensure the deliverables are increasingly adopted and leveraged by the organization over time?
A project team evaluated the performance of a new reporting system and the quantity of queries to be processed during predetermined time stamps.

Which of the following is the current status of the process?
After determining the appropriate maintenance window, which of the following should occur NEXT in the operational infrastructure change process?
Several stakeholders have declined the invitation for the kickoff of a major digital transformation protect. Which of the following actions should the project manager take NEXT?
Which of the following best describes why a project manager would decide to sign a fixed-price contract with a vendor?
A project team is working remotely from different locations across the country. As part of a lessons-learned exercise, the project manager would like to
identify the level of engagement among project team members. Which of the following would be the best tool for the project manager to use?
A car manufacturer is presenting to three vendors the abilities and qualifications required to develop the last module of a data warehouse application. The manufacturer is emphasizing the technical skills necessary to complete the project on time and highlighting its current internal IT project. Which of the following best describes this activity?
A project manager needs to develop a way to control who can modify documents, artifacts, and other data related to the product. Which of the following would be the best way to accomplish this objective?
A team is analyzing the backlog in order to decide what to include in the next sprint. Which of the following aspects is the most important for the team to take into consideration?
A project manager is meeting with stakeholders to identify objectives and success criteria. Which of the following artifacts is the project manager working on?
Several months after a project has ended, a project team member is still charging time to the project and is unable to charge time to new projects. Which of the following did the project manager neglect to do?
A fix that was not submitted to the CCB for approval was applied to an application. Although the change did not have negative consequences, the sponsors expressed concern to the project manager. Which of the following should the project manager do first to prevent this situation from reoccurring?
Several stakeholders have asked about how the requirements are being covered by the deliverables and the progress of each requirement Which of the following would be the best tool the project manager can use to provide this information to the stakeholders?
The executive leadership of an agile company has launched a new strategy. This new strategy impacts new features that are in development with the project team. Which of the following describes what the team should do next?
As a part of a project, structured cabling activities have been outsourced to another company. The agreement is that work will take six weeks to complete and will be performed at different locations. Which of the following should the project manager do? (Select two).
How does data discovery assist with data classification ' ?
A system was implemented, and testing was successfully completed. Which of the following should the project manager do NEXT?
While working with a contractor, the project manager identified a communication conflict. The contractor did not agree that there was an issue. Which of the following should the project manager and contractor review?
As part of the planning phase, a PM has defined tasks, durations, resources, and costs. Which of the following is the NEXT step in the process?
A project manager is beginning a new project that will include a high number of complex deliverables. Which of the following is the best to use to track deliverables that are yet to be completed?
A company is designing a new ERP system. The SOW includes modules for different departments. During a meeting, a stakeholder requests an additional feature. Which of the following action should the project manager take next?
Which of the following is the best example of a breach of physical security?
During the execution phase, a new PM was assigned to a project. The PM received a request to add new functionality to the system that is being developed. While the PM was conducting a preliminary review with the team, the technical lead highlighted that this functionality request was rejected during the planning phase. Which of the following documents is the best source for the PM to use to confirm this assertion?
A PM is working on the preliminary scope statement and identifies that this project has the same approach as another project that was completed last year. Which of the following actions would the PM most likely perform?
A project manager identifies stakeholders who will be impacted when a new product is delivered to the company. The project manager notices that more stakeholders will be positively impacted than negatively impacted. Which of the following actions should the project manager take?
A project manager requests the testing team to figure out if a website allows multiple users to be signed in at the same time. Which of the following testing methods would be best for the testing team to use?
An enhancement is set to be released into production, and availability issues need to be avoided. Before the release, which of the following should be the most important consideration?
A project is moving into the user acceptance testing phase. Several resources will be needed to execute different steps in the testing plan. Which of the following would be the best tool to allow the resources to remain at their desks and only react when needed?
During an agile project, a team member checked the project artifacts in order to anticipate when all the work should have been completed. Which of the following charts was the team member most likely consulting?
A project sponsor tells the project manager that new regulatory environment changes are coming in the next month. Which of the following should the project manager do next?
A project manager has noticed that one-hour status calls are consistently lasting an extra 10 to 15 minutes. Which of the following techniques would be best for the project manager to use?
A PM is responsible for implementing a new customer relationship management system and has learned that the sales organization is reluctant to utilize the new system. The organization ' s reluctance could jeopardize the success of the project. Which of the following steps should be taken to understand the adoption issues and gain organizational acceptance of the initiative? (Select TWO).
A procurement team analyzes solutions submitted from multiple vendors for the upcoming release of a required development service. The procurement team identifies a potential partnership. Which of the following would the procurement team most likely request?
A company is creating a new technology. The company is concerned that the project details could be compromised if a cloud service is used, and another company could launch the technology before the current projected delivery. Which of the following can the company do to minimize this risk?
A project manager wants to schedule a troubleshooting session for team members who are located in Germany and California. Which of the following is most important for the project manager to consider when setting up the session?
Which of the following is a consideration when determining a project ' s ESG factors?
A project team has just experienced an unexpected event and implemented a work-around. Which of the following documents should be used to record the event? (Select TWO).
Which of the following describes three-tier architecture?
Which of the following best describes a manufacturer ' s obligation to repair or change, without extra costs, any part of a product that is not functioning?
Hackers are attempting to extract large amounts of data to sell on the dark web. Which of the following steps should a project manager take next to mitigate this risk?
Which of the following should occur when implementing an IT infrastructure change that takes risks into consideration?
Which of the following is a characteristic that defines a project?
An existing application that is highly utilized by clients is moving to a new release. Which of the following environments contains this application?
A project team was instructed to refurbish old desktops. The following provides the details of the issues observed:

Which of the following issues should be addressed FIRST?
A project manager is leading the implementation of a new service for a well-known, global company for which brand image is most important. The project will rely on contracted services. As part of the request for proposal process, the project team has identified a short list of vendors to submit proposals. Which of the following items should the project team consider as a primary factor to remove a vendor from consideration?
A project stakeholder has asked the project manager to provide the performance data of a project. Which of the following should the project manager send to the stakeholder?
Which of the following is the main reason for documenting artifacts?
A PM needs to calculate the progress of the whole project scope for a presentation to the sponsor. Which of the following is the first document the PM should update?
A global shipping slowdown is causing critical raw materials needed for manufacturing to be delivered late. As a result, a project ' s production run will be delayed from the beginning.
Which of the following dependencies is most likely happening?
Which of the following provides the best justification for undertaking a project?
A project manager was not part of a contract negotiation. The project manager is concerned that stakeholders will expect the project to achieve deliverables requested in the RFP Which of the following documents should the project manager produce FIRST to start communication about the boundaries of the project?
A project manager is using an agile methodology to lead the implementation of several features that should be developed concurrently. Which of the following items should the project manager view as a concern?
When assigning access, classifying information based on sensitivity is referred to as:
Which of the following activities are performed during the closing phase? (Select three).
Due to multiple changes, the sign-off for the project scope baseline is delayed. The project sponsor has restricted the budget for this project. Which of the following should the project manager MOST likely do to move forward?
As a result of an unpredicted risk, a project manager is documenting a request in the change control log. Which of the following change control processes should the project manager do last?
Which of the following criteria would favor using the agile methodology to manage an upcoming project?
Given the following information:
Which of the following represents the critical path of the project?
A project manager is assigned to a project that has contracted with vendors. Which of the following actions should the project manager most frequently take? (Select two).
A project manager has been scheduling and facilitating project meetings, scribing the minutes, distributing the minutes, and sending agendas prior to upcoming meetings. However, the project manager is frustrated because action items are not being completed. Which of the following should the project manager do to alleviate these concerns?
A company is adapting its strategy almost every quarter, and the product might be different at the end of the project. Which of the following is the best methodology for the project manager to use?
A project is about to start; however, the client is uncertain about the desired details for the final product. Which of the following methodologies should the project manager use?
A team is working on a project that has different stages, such as initiation, planning, execution, and closure. Which of the following is this an example of?
Which of the following is a Kanban concept?
Because the project team lacks hands-on experience, the project manager has decided to involve a third-party vendor to complete the development of a product. Which of the following documents should the project manager expedite first?
Which of the following BEST describes how an organization should coordinate management of multiple related projects?
Which of the following is a capital expense?
A system is scheduled to go live, and the client signed an SLA. Which of the following elements is part of the agreement?
As a result of lessons learned, a project manager convenes a meeting to understand the poor quality of the project documentation. During the meeting, project team members provide insights from their perspectives and discussions with group members. Which of the following is the project team doing?
A project manager has been assigned to a new project. During the planning phase, the project manager needs to get an understanding of the purpose of the project. Which of the following should the project manager do?
A quality assurance team is based in three different locations To validate the project deliverables, a project manager sent the hardware for testing purposes to the team in each of the locations. Two teams confirmed the hardware arrived, but one group did not receive it because of local customs Which of the following ESG factors is the project team facing?
Which of the following statements best describes zero-based budgeting?
Which of the following are primary features provided by a standard laaS solution? (Select two).
A client made a change request. Implementing the change will cause a delay in the project and a budget overrun. Which of the following should the project manager do first?
A global franchise requests that a company provide a solution to unify its operation worldwide. Additionally, the company would like the solution to provide operation reports in real time without asking the country franchise manager for these reports. Which of the following cloud models would the company suggest to the global franchise?
A number of unexpected issues have occurred during the execution of a project that will negatively impact the timeline and costs. Which of the following would be best for the project manager to do to mitigate this situation?
A project implementation partner and the project manager disagree about completed requirements. The project manager shows the project requirements as 70% complete. The implementation partner validates that all requirements were completed. Which of the following would clarify what the project implementation partner was contractually expected to complete?
A project team member recalls a specific chat with another member that contained key information related to a previous project, which no one else on the project team is aware of. Which of the following best describes what was needed to address this concern?
Which of the following would be best to utilize when managing communications for project teams across multiple time zones?
Which of the following activities would be performed during the project closure phase when the waterfall methodology is being used? (Select two).
An organization was fined due to an audit finding that revealed a third-party vendor was able to see secured project information in a recently implemented system. Which of the following was the cause of this situation?
Which of the following is required to provide a hardware installation with a Tier 5 redundancy level?
Which of the following can help identify opportunities for future improvement following the successful closure of a project?
A project manager wants to be confident that the most crucial functions of a new software build work and that the software is ready for the next testing phase. Which of the following types of testing should be done?
A developer recommends modifying an existing portion of code that is not part of the scope and is causing low performance on the current solution. Which of the following actions should the project manager most likely take?
A company asks some vendors to provide a solution for its specific needs. Which of the following documents should the company provide?
A project manager distributes minutes after each project meeting. However, the project manager is having difficulties hosting the meetings and documenting the discussions simultaneously. Which of the following should the project manager do in order to be most efficient?
A project manager needs to ensure that the products produced during the project meet the highest quality standards and that team members understand the importance of these standards. Which of the following should the project manager do?
A team member identifies a critical issue in production. Which of the following should the project manager apply?
Which of the following should a product manager choose in order to enable collaboration between team members located in different regions? (Select two).
Someone claiming to be from a tax agency sent an email to a team member asking for access to the project repository. Which of the following BEST describes this scenario?
Which of the following best describes a benefit of the CI/CD process?
A project manager is receiving reports of the actual project expenditures and, based on this information, is making adjustments to the budget. In which of the following phases does this occur?
During the execution of a project, a project manager wanted to discover how the number of worked hours was affecting the quality of given tasks. For a two-month period, the following data was documented:
Average worked hours
Which of the following describes the result?
A product manager is producing a project status report for key stakeholders Which of the following should most likely be included? (Select two).
Which of the following should be considered first when determining the privacy management for project data?
A key stakeholder recommends to a senior developer that a new feature be added. The new feature is not part of the current requirement documentation. Which of the following is MOST likely happening?
Before a configuration can be made to a system in development, a document containing information about how the new system will interact with other systems within the organization needs to be written. Which of the following relationships best describes this scenario?
A team member needs to make an emergency update. The team member is unable to return to the office. Which of the following is the most secure way to make the update?
A new project team started work three months ago. The team members are increasing their work productivity and are comfortable asking for help with tasks. Which of the following describes the current stage of the project team?
As a result of an internal assessment, the steering committee states that the company does not currently have the required skill set or technical tools to develop a particular feature in the project. Which of the following procurement methods would help the company?
A project manager is eager to define access requirements during the initiation phase of a project. Which of the following steps should the project manager perform first?
Functional managers are reluctant to provide a project manager with resources for a project because they think the project should include a certain scope. The project manager reviews the project documentation and confirms the items the functional managers wanted to include were out of scope. Which of the following would be the best course of action for the project manager to take?
A project manager prefers to have immediate contact with team members because it allows for faster response times and more interactive discussions. Which of the following communication methods should the project manager use?
During the initiation phase, a stakeholder and the project manager discuss the business reasons and benefits of the project. The stakeholder requests these items be documented for approval. Which of the following should be used to document this information?
Which of the following BEST illustrates how team members with different roles should interact on the team?
A senior PM is working on the development of a tax application and focuses efforts to create an environment to facilitate and motivate teamwork. The team members seem to be in the storming phase. Which of the following best describes the team life cycle?
Which of the following would help a project manager identify that project goals have been reached?
A project manager does not have the power to reward team members when they accomplish something or penalize them when they fail to perform well. As a result, the project manager is having issues with team members. Which of the following describes this organizational structure?
During the execution phase of a project, the project team faced an unexpected website downtime The project manager how a brainstorming session and the team identified causes and effects tor the problem Now the project team needs to analyze and determine whether the particular cause and effect are related by using one of the following charts. Which of the following should the team use?
A)
B)

C)

D)