Pre-Summer Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

PK0-005 Questions Bank

Page: 23 / 34
Total 447 questions

CompTIA Project+ Certification (2026) Questions and Answers

Question 89

A project is not progressing as planned following the departure of the project manager. Which of the following would be the best tool to use to document this information?

Options:

A.

Issue log

B.

Risk register

C.

Change log

D.

Defect log

Question 90

Which of the following is the most important activity for the project manager during the closure of a project?

Options:

A.

Obtain project sign-off.

B.

Capture lessons learned.

C.

Document historical information.

D.

Release resources.

Question 91

A third party needs to perform a short-term task for which the duration cannot be accurately estimated and the cost cannot be calculated in advance. Which of the following should the project manager put in place before work begins?

Options:

A.

Time and materials contract

B.

Master service agreement

C.

Fixed-price contract

D.

Statement of work

E.

Cost-plus agreement

Question 92

After months of recruiting, a team finally found the right candidate for a very specific coding language assignment. Due to this delay, the team has a tight timeline without any float. A day before the candidate is scheduled to join the team, the project manager realizes the candidate has a non-compete agreement from the previous employer. Which of the following should the project manager do?

Options:

A.

Withdraw the offer to the candidate and raise this as a risk.

B.

Ignore a potential lawsuit since this is a critical project.

C.

Use a third-party company for the contract to legally avoid responsibility.

D.

Have a meeting with the project sponsor to discuss the situation.

Page: 23 / 34
Total 447 questions