Summer Certification Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Project+ PK0-005 Release Date

Page: 3 / 35
Total 460 questions

CompTIA Project+ Certification (2026) Questions and Answers

Question 9

During schedule planning, a project manager determined the logical dependencies required to complete the project. Which of the following activities should the project manager do next?

Options:

A.

Determine the stakeholders positively impacted in the project.

B.

Determine the escalation reporting tool to be used in the project.

C.

Determine the resources required to complete the tasks.

D.

Determine the total cost incurred in the project ' s execution.

Question 10

Given the following chart showing committed work (orange) vs. actual work completed (blue) across 10 sprints:

Which of the following best describes the team ' s performance?

Options:

A.

The team needs to adjust the planned work based on results.

B.

The team’s velocity is getting better.

C.

The team understands its velocity and is planning in an accurate manner.

D.

The team is doing more work than planned.

Question 11

A project manager is managing a virtual team across the country. As reported in the retrospective, the team morale has decreased due to additional production issues. Which of the following meeting tools is the best option to record results in the retrospective?

Options:

A.

Presentation

B.

Wiki

C.

Chat

D.

Polling

Question 12

A project manager is in the closing phase of an IT asset refresh project that involves the disposal of several computers. The project sponsor notified the project manager that the company recently received a penalty as a result of disposing of some computers improperly. Which of the following should have been considered during initial planning to prevent this situation?

Options:

A.

ESG

B.

PHI

C.

Pll

D.

ROI

Page: 3 / 35
Total 460 questions