Summer Certification Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

PK0-005 CompTIA Exam Lab Questions

Page: 21 / 35
Total 460 questions

CompTIA Project+ Certification (2026) Questions and Answers

Question 81

When assigning access, classifying information based on sensitivity is referred to as:

Options:

A.

Digital security

B.

Physical security

C.

Data security

D.

Operational security

Question 82

Which of the following activities are performed during the closing phase? (Select three).

Options:

A.

Requesting project charter sign-off

B.

Recognizing project team efforts and rewarding team members

C.

Working with the financial team to obtain return of investment

D.

Revoking resource credentials from the system

E.

Updating the risk register with new findings

F.

Informing the functional manager about the release of resources

G.

Monitoring project team performance

Question 83

Due to multiple changes, the sign-off for the project scope baseline is delayed. The project sponsor has restricted the budget for this project. Which of the following should the project manager MOST likely do to move forward?

Options:

A.

Communicate with the affected stakeholders.

B.

Initiate a formal change request to modify the cost

C.

Adjust the scope to stay within the cost.

D.

Set a new cost using a lightweight estimation method.

Question 84

As a result of an unpredicted risk, a project manager is documenting a request in the change control log. Which of the following change control processes should the project manager do last?

Options:

A.

Escalate to the change control board.

B.

Update the project plan.

C.

Test the implemented change request.

D.

Communicate the change deployment.

Page: 21 / 35
Total 460 questions