Spring Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

PK0-005 CompTIA Exam Lab Questions

Page: 21 / 34
Total 447 questions

CompTIA Project+ Certification (2026) Questions and Answers

Question 81

Which of the following best describes a program in the context of project management?

Options:

A.

It is a group of unrelated projects within an organization

B.

It is used to represent the daily activities of multiple projects

C.

It is a consolidation of related projects with a common goal

D.

It provides the definition of a project workload

Question 82

While working with a contractor, the project manager identified a communication conflict. The contractor did not agree that there was an issue. Which of the following should the project manager and contractor review?

Options:

A.

Scope of work

B.

Request for proposal

C.

Vendor rules of engagement

D.

Project schedule

Question 83

A project team is deciding how to break up a large project into smaller components so the project can be delivered without increasing the duration of the iteration cycles. Which of the following describes the grouping of the smaller components?

Options:

A.

An issue

B.

A goal

C.

A backlog item

D.

An epic

Question 84

A PM has identified all the resources involved in a project. The next step is to identify which resources are responsible for which tasks. Which of the following should be used to document this information?

Options:

A.

RFI

B.

RACI

C.

WBS

D.

SOW

Page: 21 / 34
Total 447 questions