CompTIA Project+ Certification (2026) Questions and Answers

Question 21

A project manager operating within a functional organizational structure is trying to avoid a project roadblock due to a mobilization fee that has not been paid to a contractor. Which of the following should the project manager do first?

Options:

A.

Authorize payment from the contingency budget.

B.

Follow up on the payment request with the payable clerk.

C.

Negotiate with the contractor to be paid later in the project.

D.

Escalate the issue to the financial controller.

Question 22

A project manager is reviewing sprint performance in a retrospective meeting.

Given the following chart, which of the following sprints shows the highest velocity?

Options:

A.

Sprint 1

B.

Sprint 2

C.

Sprint 3

D.

Sprint 4

E.

Sprint 5

Question 23

Which of the following best describes the reason a chat messaging service would be used as the primary form of communication for a project team?

Options:

A.

The team is working in different rooms within the same building.

B.

The team is working remotely two days per week.

C.

The team has members distributed around the world in different time zones.

D.

The team is based in the same office but has a large number of members.

Question 24

A project manager was concerned the results were not fulfilling the expectations at the end of the execution phase. After reviewing the SOW, the project manager realized the vendor delivered everything included in the contract. Which of the following actions should the project manager complete next?

Options:

A.

Perform a gap analysis.

B.

Escalate the issue.

C.

Submit a change request.

D.

Approve deliverables.