Helping Hand Questions for PK0-005

Page: 34 / 35
Total 460 questions

CompTIA Project+ Certification (2026) Questions and Answers

Question 133

During the initiation phase, a stakeholder and the project manager discuss the business reasons and benefits of the project. The stakeholder requests these items be documented for approval. Which of the following should be used to document this information?

Options:

A.

Statement of work

B.

Business case

C.

Requirements document

D.

Work breakdown structure

Question 134

Which of the following BEST illustrates how team members with different roles should interact on the team?

Options:

A.

SOW

B.

WBS

C.

RACI

D.

PERT

Question 135

A senior PM is working on the development of a tax application and focuses efforts to create an environment to facilitate and motivate teamwork. The team members seem to be in the storming phase. Which of the following best describes the team life cycle?

Options:

A.

The team members are in a conflict that affects their relationship.

B.

The team members perform as a well-organized unit.

C.

The team members have met and are learning about the project.

D.

The team members have completed the work and are moving on from the project.

Question 136

Which of the following would help a project manager identify that project goals have been reached?

Options:

A.

Audit report

B.

Key performance indicators

C.

Backlog

D.

Lessons learned

Page: 34 / 35
Total 460 questions