Question 37

A team is analyzing the backlog in order to decide what to include in the next sprint. Which of the following aspects is the most important for the team to take into consideration?

Options:

A.

Time to be fixed

B.

Impact to project

C.

Issue category

D.

Resource availability

Question 38

A project manager is meeting with stakeholders to identify objectives and success criteria. Which of the following artifacts is the project manager working on?

Options:

A.

Project charter

B.

Requirements traceability matrix

C.

Project communications plan

D.

Project risk register

Question 39

Several months after a project has ended, a project team member is still charging time to the project and is unable to charge time to new projects. Which of the following did the project manager neglect to do?

Options:

A.

Remove the team member ' s access.

B.

Release the project resources.

C.

Collect the stakeholders ' feedback.

D.

Have the closeout report approved.

Question 40

A fix that was not submitted to the CCB for approval was applied to an application. Although the change did not have negative consequences, the sponsors expressed concern to the project manager. Which of the following should the project manager do first to prevent this situation from reoccurring?

Options:

A.

Meet with the team and highlight the importance of change management.

B.

Roll back the process and submit a change request.

C.

Document the event as a lesson learned.

D.

Remove the team member who bypassed the CCB process.