Summer Certification Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

CompTIA Project+ PK0-005 New Questions

Page: 12 / 35
Total 460 questions

CompTIA Project+ Certification (2026) Questions and Answers

Question 45

A system was implemented, and testing was successfully completed. Which of the following should the project manager do NEXT?

Options:

A.

Validate against the scope statement and ask for sign-off.

B.

Run a control chart to ensure the quality of the deliverables.

C.

Review the risk register and close up residual risks.

D.

Start the training and handoff for the operations team.

Question 46

While working with a contractor, the project manager identified a communication conflict. The contractor did not agree that there was an issue. Which of the following should the project manager and contractor review?

Options:

A.

Scope of work

B.

Request for proposal

C.

Vendor rules of engagement

D.

Project schedule

Question 47

As part of the planning phase, a PM has defined tasks, durations, resources, and costs. Which of the following is the NEXT step in the process?

Options:

A.

Update the work breakdown structure.

B.

Review the backlog.

C.

Seek baseline approval.

D.

Establish the resource pool.

Question 48

A project manager is beginning a new project that will include a high number of complex deliverables. Which of the following is the best to use to track deliverables that are yet to be completed?

Options:

A.

Resource management system

B.

Issue log

C.

Ticketing system

D.

Backlog

Page: 12 / 35
Total 460 questions