Summer Certification Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Project+ PK0-005 Updated Exam

Page: 13 / 35
Total 460 questions

CompTIA Project+ Certification (2026) Questions and Answers

Question 49

A company is designing a new ERP system. The SOW includes modules for different departments. During a meeting, a stakeholder requests an additional feature. Which of the following action should the project manager take next?

Options:

A.

Document the change request in the change log.

B.

Communicate the change request to stakeholders.

C.

Determine the decision makers for the change request.

D.

Validate the change request.

Question 50

Which of the following is the best example of a breach of physical security?

Options:

A.

System user IDs being used by multiple individuals

B.

Printers that do not request user authentication

C.

Developers having full access to both development and production environments

D.

Project documentation that is only kept on a removable device

Question 51

During the execution phase, a new PM was assigned to a project. The PM received a request to add new functionality to the system that is being developed. While the PM was conducting a preliminary review with the team, the technical lead highlighted that this functionality request was rejected during the planning phase. Which of the following documents is the best source for the PM to use to confirm this assertion?

Options:

A.

Issue log

B.

Scope statement

C.

Risk report

D.

Change log

Question 52

A PM is working on the preliminary scope statement and identifies that this project has the same approach as another project that was completed last year. Which of the following actions would the PM most likely perform?

Options:

A.

Call the previous PM for advice on risks and issues.

B.

Ask the project sponsor to provide previous final project report results.

C.

Complete the project charter using the other PM ' s subject matter expertise.

D.

Use existing artifacts and accommodate based on the current project success criteria.

Page: 13 / 35
Total 460 questions