Question 57

During an agile project, a team member checked the project artifacts in order to anticipate when all the work should have been completed. Which of the following charts was the team member most likely consulting?

Options:

A.

Pareto chart

B.

Milestone chart

C.

Burndown chart

D.

Gantt chart

Question 58

A project sponsor tells the project manager that new regulatory environment changes are coming in the next month. Which of the following should the project manager do next?

Options:

A.

Register the issue in the issue log.

B.

Provide the change to the CCB.

C.

Implement a work-around.

D.

Add risk into the risk register.

Question 59

A project manager has noticed that one-hour status calls are consistently lasting an extra 10 to 15 minutes. Which of the following techniques would be best for the project manager to use?

Options:

A.

Meeting minutes

B.

Action items

C.

Timeboxing

D.

Follow-up notes

Question 60

A PM is responsible for implementing a new customer relationship management system and has learned that the sales organization is reluctant to utilize the new system. The organization ' s reluctance could jeopardize the success of the project. Which of the following steps should be taken to understand the adoption issues and gain organizational acceptance of the initiative? (Select TWO).

Options:

A.

Train users on the proper use of the system.

B.

Escalate the issue to the CCB

C.

Hold sessions to understand user challenges.

D.

Track system usage and report user activity.

E.

Log the issue in the project risk register.

F.

Create a memorandum of acceptable use.