CompTIA Project+ Certification (2026) Questions and Answers

Question 57

A project manager wants to be confident that the most crucial functions of a new software build work and that the software is ready for the next testing phase. Which of the following types of testing should be done?

Options:

A.

Performance

B.

Smoke

C.

Regression

D.

Unit

Question 58

A new project team started work three months ago. The team members are increasing their work productivity and are comfortable asking for help with tasks. Which of the following describes the current stage of the project team?

Options:

A.

Performing

B.

Adjourning

C.

Forming

D.

Norming

Question 59

Functional managers are reluctant to provide a project manager with resources for a project because they think the project should include a certain scope. The project manager reviews the project documentation and confirms the items the functional managers wanted to include were out of scope. Which of the following would be the best course of action for the project manager to take?

Options:

A.

Satisfy the functional managers by agreeing with their point of view in order to get the necessary resources.

B.

Advise the functional managers to submit a change request, record the issue in the issue log. and escalate the issue to the project sponsor

C.

Schedule a team meeting to discuss creative ways to incorporate the scope without having to formally submit a scope change request.

D.

Inform the functional managers that the project will produce only what has been approved and project modifications cannot be made at this point.

Question 60

Stakeholders ask the PM to provide an updated budget. Which of the following is the most important reason to update a project's budget during the execution phase?

Options:

A.

Evaluate the project's communication plan.

B.

Track and manage the project’s financial condition.

C.

Report the project’s risks and issues.

D.

Distribute resources to the project.