Month End Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

PMI PMP Exam With Confidence Using Practice Dumps

Exam Code:
PMP
Exam Name:
Project Management Professional (2024 Version)
Vendor:
Questions:
1702
Last Updated:
Apr 30, 2025
Exam Status:
Stable
PMI PMP

PMP: Project-Management-Professional Exam 2025 Study Guide Pdf and Test Engine

Are you worried about passing the PMI PMP (Project Management Professional (2024 Version)) exam? Download the most recent PMI PMP braindumps with answers that are 100% real. After downloading the PMI PMP exam dumps training , you can receive 99 days of free updates, making this website one of the best options to save additional money. In order to help you prepare for the PMI PMP exam questions and verified answers by IT certified experts, CertsTopics has put together a complete collection of dumps questions and answers. To help you prepare and pass the PMI PMP exam on your first attempt, we have compiled actual exam questions and their answers. 

Our (Project Management Professional (2024 Version)) Study Materials are designed to meet the needs of thousands of candidates globally. A free sample of the CompTIA PMP test is available at CertsTopics. Before purchasing it, you can also see the PMI PMP practice exam demo.

Project Management Professional (2024 Version) Questions and Answers

Question 1

During the final iteration of the execution phase, the project has a cost performance

index (CP!) of 0.9 and a schedule performance index (SPI) of 1.0.

How should the project manager avoid a budget shortfall?

Options:

A.

Follow the risk management plan.

B.

Reduce the team effort utilization.

C.

Look for cost-saving opportunities.

D.

Submit a change request to add to the management reserve.

Buy Now
Question 2

A customer is concerned about the time required to complete a project and is asking the project team to reduce the number of iterations required to complete the product. Which approach should the project manager take?

Options:

A.

Ask the team to raise blockers or impediments in daily meetings.

B.

Prioritize deliverables based on business value and define frequent releases.

C.

Ask the team to challenge the project estimations for a faster delivery.

D.

Prioritize the tasks with high risks to reduce the number of iterations required.

Question 3

A project manager has been assigned to a high-visibility project that has been identified as having medium complexity, based on previous similar projects. The project needs

to be delivered to the customer as a ready-to-use product .

Based on this scenario, what should the project manager focus on throughout the project life cycle?

Options:

A.

Resource management and lessons learned

B.

Time management and stakeholder engagement

C.

Cost management and risk management

D.

Stakeholder engagement and lessons learned