Labour Day Special - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

Selected PMI-RMP PMI Certification Questions Answers

Page: 9 / 10
Total 131 questions

PMI Risk Management Professional (PMI-RMP) Exam Questions and Answers

Question 33

A project manager is educating the project team on risk management regarding the role of threats and opportunities. The team decides to log the opportunities in the current project's risk register to try to maximize their chances of occurrence.

What should the project team do next?

Options:

A.

Conduct a strengths, weaknesses, opportunities, and threats (SWOT) analysis.

B.

Log the threats in the risk register to try to minimize the probability of occurrence.

C.

Log the threats in the risk register to try to maximize the probability of occurrence.

D.

Update the project management plan to ensure the results of the opportunities are captured.

Question 34

A risk management professional is currently facilitating the risk planning process with the project team. To increase the breadth of considered risks, the team wants to include high-level and strategic project risks.

What should the risk management professional do next?

Options:

A.

Perform a sensitivity analysis to the higher-level aggregate activities

B.

Develop a risk breakdown structure (RBS) identifying the potential risk categories

C.

Conduct a strengths, weaknesses, opportunities, and threats (SWOT) analysis

D.

Perform a base line Monte Carlo simulation to address overall threats to project objectives

Question 35

A new risk manager is assigned to an ongoing project, what should the new risk manager do first to assess the project environment?

Options:

A.

Review potential next steps with the project team.

B.

Review the scope of work to determine the prescribed project methodology.

C.

Review the policies and practices that are outlined in the risk management plan.

D.

Review the contract and determine the resources and project funding.

Question 36

A risk manager is reviewing documentation for a project following a risk planning workshop with project stakeholders and team members. Several items have been identified on the risk log that would be detrimental to project success, but the associated triggers cannot be managed by the organization and are unlikely to occur.

Which response should the risk manager recommend for these risk items?

Options:

A.

Mitigate

B.

Accept

C.

Enhance

D.

Exploit

Page: 9 / 10
Total 131 questions