Summer Certification Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

PMI Certification PMI-RMP Exam Dumps

Page: 18 / 21
Total 284 questions

PMI Risk Management Professional (PMI-RMP) Exam Questions and Answers

Question 69

A software development project team was preparing for a phased release when an unknown and unexpected risk occurred with potential for delaying one of the features for the planned release. The project team decided to go ahead with the release and address this missing feature at a later date. One of the end users learned about this and strongly opposed the planned release.

What should the risk manager have done to prevent this situation?

Options:

A.

Engaged the sponsor and informed them of the decision to remove the planned feature.

B.

Engaged the stakeholders more in risk management activities and decisions to get their buy-in and support.

C.

Performed proper risk identification at the project outset to ensure this risk was identified and mitigated.

D.

Created a schedule buffer in the plan to deal with unknown risks if and when they occurred. 

Question 70

A risk manager and relevant stakeholders have completed a risk response plan for a project. They have identified and planned responses to the known risks; however, a risk owner has identified and reported some residual risks not previously addressed.

What should the risk manager do first?

Options:

A.

Develop a residual risk management plan to manage the residual risks.

B.

Analyze, document, and communicate the residual risks to stakeholders.

C.

Record the residual risks in the watch list for future reference.

D.

Implement the contingency plan when the residual risks occur.

Question 71

While performing risk identification exercises, the risk manager often encounters biases from the project team. How can the risk manager accurately identify what will trigger a risk?

Options:

A.

Remind the project team to keep an open mind

B.

Review the results with the project manager afterward

C.

Review published operational experience reports

D.

Use the mean answers provided by the project team 

Question 72

An experienced and the only developer on a software implementation project will be on leave for several weeks. The risk of this critical resource ' s availability was added to the risk register. Contingencies were made for a support developer to job shadow this resource, depending on how things go prior to their leave. The project team was pleased with the backup plan and the new resource was able to shadow for a few weeks.

What should the risk manager do next?

Options:

A.

Update the risk register to indicate the risk has occurred and close out the expired risk from the register.

B.

Update, continuously monitor, and communicate the residual and secondary risks of the backup resource on the project.

C.

Hire a permanent developer to support the project, and work with the backup resource to eliminate this risk.

D.

Hire another developer to support the project, contingent on when the experienced developer returns. 

Page: 18 / 21
Total 284 questions