Spring Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

PMI PMI-RMP Questions Answers

Page: 17 / 21
Total 278 questions

PMI Risk Management Professional (PMI-RMP) Exam Questions and Answers

Question 65

In the middle of a project to improve internal workflows, the team realizes that some previously identified challenges, such as lack of stakeholder engagement, have diminished. However, the risk manager determines that concerns related to resource availability and regulatory compliance are becoming more significant.

Which measures should the risk manager implement?

Options:

A.

Concentrate on monitoring only high-visibility risks to conserve resources.

B.

Focus on tracking the risks identified at the project ' s start to maintain consistency.

C.

Reassess risk priorities carefully and update the risk register on a regular basis.

D.

Delegate all monitoring responsibilities entirely to individual team members for efficiency.

Question 66

An undocumented risk is realized during the rollout of a new product line important to the company. The product owner escalates this matter to the company president, who expects all risks to be documented in the project risk plan.

How should the risk manager address this concern?

Options:

A.

Risks are documented to the practicable extent possible.

B.

Probability of the risk was very low. so the risk was not documented.

C.

Impact of the risk was assessed to be insignificant, so the risk was not documented.

D.

A similar risk never occurred in the past, so it was not considered. 

Question 67

Members of a project team are not taking their risk management responsibilities seriously. They do not consider risk management as primary to the project’s success and do not believe that the benefits are significant.

What should the risk manager do?

Options:

A.

Schedule a meeting to review and develop realistic risk thresholds with the project team.

B.

Motivate and influence the project team with risk engagement activities like workshops.

C.

Ensure that risk management responsibilities are clearly identified in the risk management plan.

D.

Ensure that the risk language used by all stakeholders is consistent with the risk management plan.

Question 68

A mega facility development project is evaluating some options to achieve the project schedule and budget. Each option ' s success is driven by multiple quantifiable factors.

What should the project manager do to evaluate and select the best option based on costs and probabilities?

Options:

A.

Perform a FMECA fault tree analysis

B.

Conduct a sensitivity analysis

C.

Perform a decision tree analysis

D.

Conduct an analytic hierarchy process

Page: 17 / 21
Total 278 questions