Big Halloween Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Free PMI-RMP PMI Updates

Page: 4 / 20
Total 264 questions

PMI Risk Management Professional (PMI-RMP) Exam Questions and Answers

Question 13

A project team has just initiated a large project to move an organization's headquarters to another location. The risk manager has scheduled a risk identification session but notices that the project charter, work breakdown structure (WBS). and scope statement are not available.

What should the risk manager consider?

Options:

A.

Aligning with the project manager to hold an open brainstorm session with all stakeholders will suffice.

B.

The ideal solution is to find alternate documents that provide good visibility on the environment.

C.

The risk identification process can be carried out as long as the project statement is available.

D.

Risk evaluation will be challenging without these elements as a frame of reference.

Question 14

A project manager is working on a construction project. Based on past experience, the project manager identifies a risk that a supplier of a critical material may not deliver on time. The project manager has already accounted for this risk in the risk management plan. If this risk materializes, the project manager plans to procure the material from a different supplier. A potential risk in this plan is that there may be differences in the material provided by the first and second supplier.

What type of risk is this?

Options:

A.

Residual risk

B.

Primary risk

C.

Secondary risk

D.

Normal risk

Question 15

A project manager has determined that they cannot outsource work nor eliminate the scope. They also discover that they cannot buy insurance or mitigate the risk.

What should the project manager do?

Options:

A.

Avoid the risk

B.

Transfer the risk

C.

Ignore the risk

D.

Accept the risk

Question 16

A risk manager has been assigned to a new project and learns that stakeholders and project team members are spread across multiple time zones. Furthermore, many project team members have not worked together in the past. These items are identified as potential risks and added to the risk register.

How should the risk manager improve collaboration during risk planning?

Options:

A.

Gather risk information from all parties and compile all submissions into a strength, weaknesses, opportunities, and threats (SWOT) analysis template.

B.

Create a repository for project documents and related artifacts that can be accessed by all parties.

C.

Communicate program metrics to all parties and create a scorecard to measure the effectiveness.

D.

Work with the project manager to develop a start-up workshop and colocate the team if permitted. 

Page: 4 / 20
Total 264 questions