Question 49

The scope of a large mobile network deployment project includes equipment to be furnished by the customer. The risk manager is concerned that the equipment delivery might be delayed, causing additional delays in the project.

What should the risk manager do?

Options:

A.

Follow up on the schedule and assess the best course of action if any delays are detected.

B.

Ensure the equipment constraint is well-documented and manage it as a high-impact project risk.

C.

Raise the issue with the project sponsor so it can be handled as a sales or contractual matter.

D.

Obtain a signed commitment from the customer that equipment will be delivered on time. 

Question 50

During the construction of a housing development, a project team realizes they exceeded their materials budget during the first of three execution stages. The risk manager observed that the team did not notice that the cost of the materials increased due to continuous inflation in the steel market.

What could have been done during project planning to avoid overspending?

Options:

A.

Met weekly with the finance team to monitor the cost

B.

Communicated with the stakeholders that the project costs might increase

C.

Properly documented the triggers and actions for the risk

D.

Engaged with the sponsor to buy the steel in advance of the project 

Question 51

During a project's planning phase, the project team identifies a potential supplier delay and marks it as a significant risk. A risk manager is tasked with effectively monitoring this risk.

What should the risk manager document as the risk trigger?

Options:

A.

The probability and impact rating of the supplier's delay on the project

B.

The response strategy, such as increasing inventory or finding an alternative supplier

C.

The specific event or condition, such as the supplier missing a delivery deadline

D.

The threshold for acceptable delay, such as a maximum of three days before impacting project milestones

Question 52

A risk manager is assigned to a mobile network deployment project with a strict contractually agreed-on schedule. One of the key risks identified has materialized. There is insufficient staffing because critical resources are dedicated to strategic projects in the organization. The risk manager expected the resource manager to notice this, but the resource manager thought the project experts would be alerting the team during the project.

What should the risk manager do to prevent this from happening again?

Options:

A.

Document the risks and response actions in a clear manner.

B.

Communicate with the project manager on the topic.

C.

Assign owners who will be fully accountable to managing the risks.

D.

Define the response plans and take the lead in implementing them.