Summer Certification Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

PMI-RMP VCE Exam Download

Page: 3 / 21
Total 284 questions

PMI Risk Management Professional (PMI-RMP) Exam Questions and Answers

Question 9

A risk manager is preparing for the first meeting with their project sponsor on a potential project for a large client. The risk manager reviews their newly developed project risk register to identify any risks that should be analyzed further and begins by prioritizing the probability column based on the following criteria:

1 = Very Low

2 = Low

3 = Medium

4 = High

5 = Very High

What type of risk analysis is the risk manager performing?

Options:

A.

Scenario-based risk analysis

B.

Quantitative risk analysis

C.

Qualitative risk analysis

D.

Monte Carlo analysis 

Question 10

The project director and project manager have met with the board and determined that the project has depleted the entire contingency reserve and has started eroding the profit margin.

The project manager would like the risk manager to take full advantage of opportunities.

Which response should the risk manager take?

Options:

A.

Mitigate

B.

Accept

C.

Transfer

D.

Exploit

Question 11

During the planning phase of a construction project, the project manager is assessing the project environment for potential threats and opportunities, including market conditions, regulatory requirements, and technological changes. The risk manager is asked to support this assessment to ensure risks are consistently identified and analyzed.

What should the risk manager do?

Options:

A.

Coach the project manager on evaluating environmental factors using standard risk assessment techniques.

B.

Assign a specialized environmental expert to independently analyze external project factors separately.

C.

Collaborate with the project manager to define and apply appropriate risk analysis processes and tools.

D.

Recommend updating organizational process assets before completing the environmental risk assessment.

Question 12

During the early planning stages of an AI-based software development project, the project team begins outlining the risk management activities. The risk manager notices that key stakeholders, such as data scientists, product owners, and external data vendors, lack a shared understanding of risk management principles.

What should the risk manager do to educate stakeholders?

Options:

A.

Conduct risk workshops tailored to all stakeholders.

B.

Invite all stakeholders to daily coordination meetings.

C.

Distribute risk-policy documents to all stakeholders.

D.

Provide project management training to all stakeholders.

Page: 3 / 21
Total 284 questions