Labour Day Special - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

PMI PMI-RMP Actual Questions

Page: 10 / 10
Total 131 questions

PMI Risk Management Professional (PMI-RMP) Exam Questions and Answers

Question 37

Members of a project team are not taking their risk management responsibilities seriously. They do not consider risk management as primary to the project’s success and do not believe that the benefits are significant.

What should the risk manager do?

Options:

A.

Schedule a meeting to review and develop realistic risk thresholds with the project team.

B.

Motivate and influence the project team with risk engagement activities like workshops.

C.

Ensure that risk management responsibilities are clearly identified in the risk management plan.

D.

Ensure that the risk language used by all stakeholders is consistent with the risk management plan.

Question 38

A company is preparing a formal response to bid for an infrastructure engineering, procurement, and construction project. When should a risk register be developed to identify risks?

Options:

A.

During the project execution phase to allow the project manager to understand the risk attitudes of stakeholders.

B.

When a client project kick-off meeting is held to introduce risk assessment process to the client.

C.

Before a formal bid response is provided to the client to gain a greater understanding of the project’s risk profile.

D.

After a project budget is set up with a purchase order to charge hours for a risk workshop.

Question 39

After starting a new pipeline project, a risk manager schedules an initial meeting with the project sponsor. For the meeting, the project sponsor requests a presentation of the risks that have the most impact on achieving the project objectives.

What should the risk manager do to facilitate the sponsor's ask?

Options:

A.

Monte Carlo analysis

B.

Qualitative risk analysis

C.

Sensitivity analysis

D.

Quantitative risk analysis

Page: 10 / 10
Total 131 questions