Pre-Winter Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

PMI Certification PMI-RMP Book

Page: 8 / 22
Total 333 questions

PMI Risk Management Professional (PMI-RMP) Exam Questions and Answers

Question 29

The project manager asks the risk manager to determine the initial risk assessment for a six month initiative that is about to kick-off. Which two artifacts will help the risk manager conduct the related analysis? (Choose two.)

Options:

A.

Work breakdown structure (W & S)

B.

Project organizational chart

C.

Configuration management plan

D.

Brainstorming

E.

Monte Carlo analysis

Question 30

During the planning phase of a construction project, the project manager is assessing the project environment for potential threats and opportunities, including market conditions, regulatory requirements, and technological changes. The risk manager is asked to support this assessment to ensure risks are consistently identified and analyzed.

What should the risk manager do?

Options:

A.

Coach the project manager on evaluating environmental factors using standard risk assessment techniques.

B.

Assign a specialized environmental expert to independently analyze external project factors separately.

C.

Collaborate with the project manager to define and apply appropriate risk analysis processes and tools.

D.

Recommend updating organizational process assets before completing the environmental risk assessment.

Question 31

A project manager managing a high-risk rating project was just informed that one of the key project resources has decided to leave the organization. The project manager asks the risk manager for their recommendations. The risk manager previously identified this as a risk and had created a transition plan to enable another resource to carry out the same duties. The risk manager was informed that by transitioning the responsibilities to the new resource, new risks to the completion dates of other project-related tasks appear.

What should the risk manager advise the project manager?

Options:

A.

Escalate the new risks immediately to the project stakeholders to ensure proper risk communication is in place.

B.

Address these secondary risks as per the risk management plan

C.

Apply a risk acceptance strategy to the new risks as there is no risk response plan.

D.

Update the risk management plan with the new probabily/impact and change the response.

Question 32

A project team working on a large software deployment project for a few months has been able to prevent a technical risk from occurring. However, an incident took place and triggered the technical issue.

What should the risk manager do?

Options:

A.

Execute the risk response plan defined for the risk.

B.

Postpone the software launch to sort out the technical issue.

C.

Assess the impacts and define the response actions with the subject matter experts (SMEs).

D.

Meet with the project manager to revisit the project schedule.

Page: 8 / 22
Total 333 questions