Summer Certification Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Free Access PMI PMI-RMP New Release

Page: 7 / 21
Total 284 questions

PMI Risk Management Professional (PMI-RMP) Exam Questions and Answers

Question 25

A project is underway to implement a new customer support software. During testing, the risk manager discovers that the integration with the existing customer relationship management system is more complex than initially planned, potentially delaying the project. The risk manager needs to update project documents to reflect this new information.

Which steps should the risk manager consider when updating relevant project documents?

Options:

A.

Update the issue log with relevant information as the immediate concern for key stakeholders.

B.

Assume the delay will not affect the timeline and continue with the current scheduled activities.

C.

Update the project documents after the work has been completed and formally accepted.

D.

Assess the delay with the technical team, update the schedule and risk register, and inform stakeholders.

Question 26

An eco-friendly sustainable textile-dyeing project has begun, with a focus on identifying and managing environmental risks. The risk manager, collaborating with the project manager, is tasked with reviewing and updating the project’s risk management plan. To inform this process, the risk manager needs relevant insights specifically related to environmental risk factors.

What should the risk manager do?

Options:

A.

Review process documents from Six Sigma to identify areas of process inefficiency.

B.

Refer to standards for information security management systems to ensure compliance.

C.

Consult environmental enthusiasts for informal feedback on potential risks.

D.

Use prompt lists to systematically identify and analyze environmental risk factors.

Question 27

In a large enablement project with strict time lines, risks need to be closely monitored. The risk manager publishes reports comparing planned enablement sessions with actual enablement sessions, which help identify potential risks to be addressed.

Which technique is the risk manager using?

Options:

A.

Variance analysis

B.

Residual impact analysis

C.

Sensitivity analysis

D.

Reserve analysis 

Question 28

A financial services company has implemented a risk response plan to mitigate potential cybersecurity threats. The project team has conducted a series of tests to ensure the new security measures are effective. However, some executives have expressed concerns about the impact of these measures on daily operations.

What should the risk manager do?

Options:

A.

Facilitate a risk identification session on security measures with the company executives.

B.

Organize a stakeholder workshop to discuss the effectiveness of the new security measures.

C.

Implement additional security measures to address the concerns expressed by the executives.

D.

Acknowledge the concerns and focus on monitoring the effectiveness of the new security measures.

Page: 7 / 21
Total 284 questions