Spring Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Newly Released PMI PMI-RMP Exam PDF

Page: 6 / 21
Total 278 questions

PMI Risk Management Professional (PMI-RMP) Exam Questions and Answers

Question 21

A project with impending risks has 12 deliverables as subprojects, which will be executed in three different locations involving multiple stakeholders. What should the risk manager do to organize the prevailing risks?

Options:

A.

Combine individual and focus groups to identify risks and create the overall risk register.

B.

Use focus groups to conduct group risk assessments of the project to identify risks.

C.

Request individual assessments of the project and its deliverables to identify risks.

D.

Use the external risk assessment of the project and its deliverables to identify risks.

Question 22

A project manager is leading a complex, high-risk construction project in the city center. To address risk based on lessons learned from similar past building projects, the risk manager assigns a team member to assess and confirm risk thresholds for the project.

What should the risk manager do?

Options:

A.

Develop risk assessment processes and tools to quantify risk thresholds.

B.

Work with stakeholders to achieve consensus on risk thresholds.

C.

Use subject matter experts and historical data to estimate risk thresholds.

D.

Review regulatory requirements and the contract to identify risk thresholds.

Question 23

A project manager is working on a high priority and high profile project. The project team had identified three opportunities, and after analysis, risk responses were recorded. Although risk responses were adequate for the identified opportunities, two of those opportunities were not acted upon. During the risk audit, the project manager found out that several of the planned risk responses were not implemented.

What should the project manager have done to avoid this?

Options:

A.

Provided regular training to the risk owners for plan implementation

B.

Determined risk triggers and thresholds in the risk response plan

C.

Increased communications to influence stakeholder risk responses

D.

Updated the project schedule, adding risk owner implementation tasks.

Question 24

The risk manager loaded the risk register, built the risks into the simul-ation software, and ran the Monte Carlo analysis. The P80 and P90 end dates are the same as the deterministic date.

What should be the risk manager ' s next step?

Options:

A.

Check the schedule for constraints

B.

Use the P90 date on the risk report

C.

Decrease the number of iterations

D.

Decrease the risk consequences

Page: 6 / 21
Total 278 questions