Pre-Winter Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Newly Released PMI PMI-RMP Exam PDF

Page: 6 / 22
Total 333 questions

PMI Risk Management Professional (PMI-RMP) Exam Questions and Answers

Question 21

The scope of a large mobile network deployment project includes equipment to be furnished by the customer. The risk manager is concerned that the equipment delivery might be delayed, causing additional delays in the project.

What should the risk manager do?

Options:

A.

Follow up on the schedule and assess the best course of action if any delays are detected.

B.

Ensure the equipment constraint is well-documented and manage it as a high-impact project risk.

C.

Raise the issue with the project sponsor so it can be handled as a sales or contractual matter.

D.

Obtain a signed commitment from the customer that equipment will be delivered on time. 

Question 22

During a risk identification session, the risk manager notices that subject matter experts (SMEs) are reluctant to participate because some risks could expose the poor maturity of processes in other business units. Which risk analysis technique should the risk manager use?

Options:

A.

Strengths, weakness, opportunities, and threats (SWOT) analysis

B.

Delphi technique

C.

Decision tree analysis

D.

Probability impact matrix

Question 23

The project manager performed ' a variance analysis on the project during the execution phase. The variances were shown as increasing

What does this result imply?

Options:

A.

The uncertainty and risk are increasing.

B.

The project schedule is lagging behind.

C.

There is no potential for future deviation.

D.

The project is over budget.

Question 24

After a number of risk workshops, risks have been identified. Which is the first element the risk owner should look for in the response plan to help mitigate the risks?

Options:

A.

Probability of a response triggering a secondary risk

B.

How the response will affect the quality of the components

C.

If the risk response is tied to an activity on the critical path

D.

Verify due dates for the actions have been identified

Page: 6 / 22
Total 333 questions