Summer Certification Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Legit PMI-RMP Exam Download

Page: 12 / 21
Total 284 questions

PMI Risk Management Professional (PMI-RMP) Exam Questions and Answers

Question 45

When performing a risk analysis, a risk manager identifies not only negative risks but also positive risks, which might bring added value to the project. What should the risk manager do next?

Options:

A.

Prioritize opportunities as they are likely to bring benefits to the project.

B.

Analyze the risks and add them to the risk register to continue the process.

C.

Create a separate project to exclusively manage positive risks and threats.

D.

Assign separate stakeholder groups for positive risks and negative risks.

Question 46

A project manager managing a high-risk rating project was just informed that one of the key project resources has decided to leave the organization. The project manager asks the risk manager for their recommendations. The risk manager previously identified this as a risk and had created a transition plan to enable another resource to carry out the same duties. The risk manager was informed that by transitioning the responsibilities to the new resource, new risks to the completion dates of other project-related tasks appear.

What should the risk manager advise the project manager?

Options:

A.

Escalate the new risks immediately to the project stakeholders to ensure proper risk communication is in place.

B.

Address these secondary risks as per the risk management plan

C.

Apply a risk acceptance strategy to the new risks as there is no risk response plan.

D.

Update the risk management plan with the new probabily/impact and change the response.

Question 47

An organization with a portfolio of unique business functions kicks-off a performance improvement project across the entire organization. There are a large number of stakeholders the project team will need to consider during risk identification.

What three actions should the risk manager ensure the project team performs during risk identification? (Choose 3)

Options:

A.

Develop checklists based on historical information

B.

Conduct interviews, meetings, and focus groups

C.

Assign a different risk manager for each portfolio unit

D.

Employ brainstorming to generate spontaneous ideas

E.

Perform qualitative and quantitative risk analyses 

Question 48

A risk manager is collaborating with project stakeholders and the project team to identify risks in a construction project. The risk manager intends to use an approach that engages stakeholders based on information, such as scope baseline and project estimates, while also determining risk impacts based on this approach.

Which risk identification approach should the risk manager use to achieve this goal?

Options:

A.

Strengths, weaknesses, opportunities, and threats (SWOT) analysis

B.

Brainstorming technique

C.

Delphi technique

D.

Assumptions and constraints analysis

Page: 12 / 21
Total 284 questions